of the changes in wetlands impacts justifies a supplemental environmental impact statement and supplemental NEPA and SEPA review process.
None of the various revisions of the
applicant’s wetland assessment and impact analysis [i]
[ii]
[iii]
include any substantive discussion of the impacts of removal of these wetlands
on water quality in Miller, Walker or Des Moines Creek. Section 4.3.4 in the latest iteration of the
Port’s BA limits discussion of impacts to riparian areas near Miller Creek to
two brief paragraphs that begin with the bald assertion "Negative Impacts
to the riparian wetlands will not occur."
Section 3.1.3 (p.3.11) of the document then takes a "blame the
victim" approach toward the existence of riparian wetlands near the
proposed project and states: "Riparian wetlands may act as sediment source
due to bank erosion that often occurs during periods of high stream
flow." We would add, yes, this is
probably true and a good reason not to allow a project that would deposit 20
million cubic yards of material upstream providing sediment and destroying
these and adjacent riparian wetlands.
The Wildlife Hazard Management Plan [iv]
submitted by the project proponent contains no analysis of historical
incidences of bird strikes at Sea-Tac airport.
The lack of any historical record of bird-aircraft strike hazard (BASH)
at Sea-Tac indicates the FAA's alleged objection to in-basin mitigation of
wetlands destroyed by the Port of Seattle's proposed projects is unfounded.
It is reasonable for the agencies
considering this issue to compare data concerning the bird-strike issue with
records collected by agencies to adopt a regulatory framework. We are astonished to hear that the FAA is
apparently not interested in such data. [v]
We are additionally concerned the
project proponent has not considered provisions of the FAA Advisory Circular
concerning hazardous wildlife attractants that are particularly applicable in
this situation:
Exceptions
to locating mitigation activities outside the separation identified in the
siting criteria may be considered if the affected wetlands provide unique
ecological functions, such as critical habitat for threatened or endangered
species or groundwater recharge. (AC
150/5200-33, Section 2-4.b (3))
A 'no-build'
alternative is a "practicable alternative" and would be less damaging
than the Applicant's Project, & at least as effective. Every federal agency is
obligated "to minimize the destruction, loss, or degradation of wetlands,
and to preserve and enhance the natural and beneficial values of wetlands in
carrying out the agency's responsibilities for ... providing Federally
undertaken, financed, or assisted construction and improvements." Federal agencies are prohibited from providing
funding or other assistance for the construction of projects in wetlands unless
they find "(1) that there is no practicable alternative to such
construction, and (2) that the proposed action includes all practicable
measures to minimize harm to wetlands which may result from such
use."
Section 404 of
the Clean Water Act requires that anyone proposing to discharge dredged or fill
material into navigable waters must first obtain a permit from the U.S. Army
Corps of Engineers ('Corps'). "Navigable waters" are defined as
"waters of the United States," which have been interpreted by the
Corps to include "wetlands."
Because construction of the proposed third runway and associated Master
Plan Update development actions would affect wetlands, these actions cannot be
undertaken unless it is affirmatively determined (a) that there is no
practicable alternative to such construction; and (b) that the proposed action
includes all practicable measures to minimize harm to wetlands which may
result.
Since the close
of comments on the prior application, two important groups of additional facts
have come to light bearing on the need for the Project. These new facts, taken together with facts
previously known, make it wrong to grant the certification and permit sought by
the Applicant
As a matter of relevant background,
before coming to the new facts, it is important to realize that the alleged
‘delay’ problem is non-existent, or at least not proven to exist..
One way of thinking about this issue is
as follows. First, settle on a
definition of ‘delay’ that is reasonable, that the airlines agree with, that
commercial air travelers would view as reasonable, and that can be measured at
Sea-Tac Airport & other major airports in the U.S. The definition should be designed to capture
& report separately data on elements of ‘delay’ that are attributable to
poor weather at Sea-Tac and to capture & report separately elements of ‘delay’
that are NOT attributable to poor weather at sea-Tac. Second, reach agreement on a way to define all other
delays, as air travelers and airlines experience delay, & to agree on a way
to measure such delays. It is important
to be able to distinguish between & to compare (a) Sea-Tac related delays that arguably would
support the proposal for another runway, (b) Sea-Tac related delays that cannot
be cured by construction (such as passengers’ difficulties in reclaiming
baggage), and (c) delays that are experienced by Sea-Tac travelers that are not
Sea-Tac related. It is essential to
have some means of comparing the various types of delay with one another, for
purposes of costs-benefit analysis, for ensuring that huge amounts of money are
not spent on problems that are either relatively unimportant or that could be
dealt with by other, less-costly, less-damaging methods. Third, do a trial run on data
collection. It would be useful to run
the model or measurements at several other airports simultaneously with the
Sea-Tac experiment, to ensure that no significant block of delay related to
more than one airport (as, delays on a flight from Chicago to Sea-Tac) is being
omitted & likewise to ensure that individual delay elements are not
double-counted. Fourth, after review of
a sample measurements & necessary refinement in the model, do the work
again & subject it to public comments, to ensure that the method has public
acceptance & credibility. It will
be seen later in this discussion that the method for measuring delay that the
proponents used in this instance does not meet any of the criteria suggested
here, & is of dubious value.
What actually happened was that the
proponents of the Project have trotted out vast claims of delay (never
supported by independent studies, or any public process to develop such
studies). The general public, &
relevant planning agencies, were expected to accept the claims without
criticism or comprehension. The
methodology, if any, for making these claims was not revealed. The methodology for making claims of dollar
savings was not revealed. Delay was
undefined. A project originally costing
$225 million was to be approved on the basis of mere assertions.
The claims as to extent & cost of
‘delay’ made by the proponents were so great as to defy common sense. Seemingly, commercial airlines were losing
hundreds of millions of dollars.
Airlines were pig-headedly incurring vast losses to fly into Sea-Tac,
& were doing nothing to change their ways in order to avoid those losses. This analysis on its face was unreasonable.
Therefore, RCAA has pressed hard
throughout the history of the third-runway effort for (1) a definition of
'delay' as the FAA & Port use it for purposes of justifying the Project,
(2) a rational explanation of the proponents' position that measures short of
construction will not meet the problem -- whatever it is; (3) a reasoned cost-benefit analysis.
Ecology should also seek understanding
on these topics. It would be
inappropriate to grant a permit on the basis of unexamined, unexplained claims
by the Project’s proponents. Unless
actual delay can be demonstrated, there is NO justification for the filling of
wetlands, for the expenditure of hundreds of millions of public dollars. In this regard, it will be helpful to
consider the last round of dialogue on this point -- RCAA Comments on the point
in the FEIS, and the responses of the Port and FAA. The first comment to consider is the one in which we sought to
learn how "delay" was measured.
Comment II-39:
Purpose & need; measuring delay. It is entirely unclear from Chapter II of
the DEIS which techniques were used to measure or to assess delay at Sea-Tac in
the various studies mentioned. We are
aware of three different techniques, known as ATOMS, ASQP, & SIMMOD, &
that they yield very different results as to delay. But the details of each are unclear to us, & the average lay
reader of the DEIS would not have a clue that there are competing measurement
or assessment methods, or that different studies have produced different
results. What is measured? Who does the measuring? Are various causal factors considered? reported?
Who decides whether a delay is caused by weather, by aircrew problems,
by groundside problems? What happens if
one delay has multiple causes? What
happens if no one is sure what cause was?
At a minimum, the FEIS should pull up from the studies on which the lead
agencies rely sufficient detail to enable the intelligent lay reader to know
what was done, why, & how, to measure the delay, & to understand what
the controversy is about the results reported in the DEIS, & why the DEIS
& FEIS accept a particular set of figures.
(In this
context, we respectfully suggest that the reviewers of the Corps and Ecology
are in much the same position that our review teams are & have been: intelligent but lay readers, dependent on
the 'experts' to provide accurate, understandable information.) We thought (& still think) that our
Comment II-39 was a reasonable comment, deserving of a forthcoming response. But this is what we got:
Comments R-3-17: The
Regional Commission on Airport Affairs and Mr. Frause asked several questions
concerning the definition of delay.
Response: Aircraft delay is one measure of the
operating efficiency or performance of an airport system or its various
components. It is defined as the
difference between the actual time required for aircraft to pass through the
system (or a component of the system, like the enroute airspace) and the
optimal time achievable without constraints such as poor weather at the
destination airport, lack of adequate runway or taxiway facilities, or airspace
interactions with other airports.
Aircraft delay results from multiple aircraft competing for limited
facilities and can be influenced by a number of factors, such as:
· Ceiling
and Visibility Conditions
· Airfield
Physical Characteristics
· Air
Traffic Control Procedures, and
· Aircraft
Operational Characteristics
When dealing
with aircraft delay, it is important to understand that aircraft are often
delayed at a location that is not the source of the delay. By means of FAA Central Flow Control
Procedures, aircraft are routinely held at the origin airport rather than in
airspace holding patterns during periods of reduced arrival acceptance rates at
the destination airport. Accordingly,
when weather conditions in Seattle [sic] preclude the use of dual approaches,
aircraft destined for Sea-Tac are held either at the gate or on the airfield of
the origin airport. Such delays are
often attributed to the departure from the origin airport, rather than the
arrival into Sea-Tac Airport. (emphasis added)
The metrics
used to measure delay vary widely and depend on the intended use of the
data. For example, the FAA’s Air
Traffic Operations System (ATOMS) is an operational and tactical planning tool
used to support decisions about real time air traffic control procedures and
the deployment of air traffic control personnel and other resources. As such, ATOMS, is used to collect data on
the number of flights delayed 15 minutes or more during any one of the four
stages of flight: departure, air traffic management, enroute, and arrival. These four segments coincide with the air
traffic control division of workload used throughout the National Airspace System
(NAS). For example, a flight that incurs
14.5 minutes of delay in the departure phase, 14.5 minutes of delay due to air
traffic management, 14.5 minutes enroute and 14.5 in the arrival phases (a
total flight delay of 58 minutes) would not be counted as a delayed flight
using the ATOMS methods. Since ATOMS
was not designed to assist with decisions about airport improvements, such as
the proposed new runway at Sea-Tac Airport, it does not provide useful
information about the source of a particular delay, nor does it quantify the
aggregate minutes of delay experienced throughout the NAS due to constraints at
a particular facility.
On-time
performance, as reported through Airline Service Quality Performance (ASQP), is
another measure of system performance that is often confused with delay.
So, on the basis of that response, what measure of delay was being used by the proponents, & how was delay defined?
We suggested in our Comment II-35 to
the Master Plan Update DEIS that air carriers would not behave in an irrational
manner by forcing peak-period flights with serious delays, but would, rather,
spread their flights, compress their passenger loads, & in other ways
behave sensibly. Thus, projecting
crowding & costly delays without taking into account the predictable
behavior of the players was & is erroneous. The proponents’ response to that (Response 4-7) was that
demand-management alternatives were discussed in the Flight Plan EIS -- by no
means the same thing!
Our Comment II-36 suggested "that
a combination of higher load factors, a modest increase in flights using the
existing two-runway configuration, high-speed rail travel, technical advances,
etc." would accommodate the projected boarding increases found in the
Master Plan. The Response only
addressed high-speed rail, & found that non-feasible on the basis of the
decision of the Expert Arbitration Panel on that point (the Panel's order of 8
December 1995). The Response failed to
notice that the reason for the Panel's conclusion was that there was no entity
pushing for high-speed rail in Washington; the Response failed to note that
directly after that order was released the Department of Transportation changed
position radically, & announced a whole series of initiatives for
increasing high-speed rail travel -- i.e., the problem that concerned the Panel
had essentially gone away. So, we
repeat: a combination of higher load factors, a modest increase in flights
using the existing set-up (20,000 per annum), increases in rail travel
(especially high-speed rail), technical advances in aviation should suffice to
obviate bad-weather arrival delay. We
would add that administrative measures post arrival at the Airport, aimed at
speeding the departure of arriving passengers would work wonders in terms of
reducing the actual delays experienced by incoming travelers. This is the least costly way of dealing with
the problem – if it exists.
Ecology must consider the use of
technological improvements that will permit aircraft landings in poor weather
conditions.
Some may disagree with our analysis infra, showing that the 'delay' problem
is so ill defined as to be non-existent.
But even if there is some bad-weather arrival delay, the proposed
solution to it is not the appropriate one.
Other less costly and less environmentally damaging alternatives are
available.
The problem, put simply, is that with
the existing two major runways being only 800 feet apart, commercial aircraft
cannot use both runways simultaneously and independently when aircraft are
required by reason of weather to land by instrument rules. Air-traffic controllers must treat those two
runways as part of one system. And FAA
regulations do not permit two jetliners to land simultaneously in poor weather
side by side, with only an 800-foot separation. Much larger separations are required, the amount increasing as
visibility worsens. Even with flight
instruments, the FAA for safety reasons requires a substantial separation,
owing to the imprecision of the instruments.
The 2500-foot separation between first and third runway is the least
distance that FAA will allow under unfavorable flying conditions -- hence the
location of the proposed new runway.
However, the quality of flight
instruments has taken a quantum leap since the inception of the third-runway
project. The best-known new technology
is GPS, global positioning system. The
web of 24 Department of Defense satellites around the planet can be tapped to
locate a GPS instrument with enormous precision. The instruments are inexpensive -- ordinary hikers and
mountaineers can afford to carry scaled-down versions in their backpacks. Aircraft equipped with avigational-grade
instruments are able to land safely in conditions of zero visibility, and right
on the mark. The instrumentation has been
tested repeatedly, with huge success.
We include with this submittal a copy
of the September 1, 1999 article published in the Wall Street Journal (“Airline
Seeks OK on Tool to Beat Fog”), describing the
use of global positioning satellite technology in conjunction with navigational
equipment now being provided with commercial aircraft, which permits landings
in reduced visibility conditions. This
technology has been under development by the air transportation industry for
several years and is now being implemented in commercial aircraft at the
nation’s airports. The article discusses its proposed use at San Francisco
airport where parallel runways are spaced only 750 feet apart, comparable to
the 800 foot spacing between Sea-Tac’s runways. The article reports an FAA operations inspector stating the
technology “will be the standard cockpit equipment of the future.” Ecology must consider utilization of this
technology as an alternative to the destruction of wetlands for the runway
project.
Alaska Aircraft announced as long ago
as September 1996 that it would equip the 25 Boeing 737-400s in its fleet with
GPS avionics, at a cost of only $10 million.
Coupled with the GPS instruments would new Enhanced Ground Warning
System technology (to ensure that the arriving aircraft down exactly at the
runway surface. Once installed, of
course, such instrumentation is useable everywhere. Alaska, it may be noted, is the largest carrier by volume at
Sea-Tac. GPS will solve the bad-weather
arrival problem at Sea-Tac, as soon as FAA's rules catch up with technology.
Other flight-instrumentation and
control technologies are being developed that are independent of the satellite
systems. Best known is the FMS, which
permits air-traffic controllers to keep aircraft in extraordinarily narrow
corridors, with deviations of only a few feet from side to side. This technology, too, is available, and like
GPS will lead to new rules allowing side-by-side arrivals at distances never
before thought feasible. These
technologies have advanced greatly in understanding and acceptance, even since
December 1997. The previously cited
article from the Wall Street Journal refers to such additional methodologies as
RNP (required navigational performance) and ground-based high-definition radar.
At the very least, these & other
new technologies mean that a new runway could be built within the
perimeter of the present Airport campus, & meet any bad-weather delay
problem that might exist. At best,
these technologies should lead to the ability to use the two main runways at
Sea-Tac as they now are with the same efficiency in poor weather as now exists
in good weather. Either way, the
wetlands filling proposal of the Applicant will not be needed.
The Corps and Ecology should require a
very clear explanation from the Applicant as to why a technological solution to
the delay issue is not being pursued.
The Corps and Ecology should conduct its own study of the issue,
consulting with flight-instrument firms (Honeywell and Canadian Marconi, among
others), major air carriers, airports where GPS field trials have been
conducted, and so on. For a cost far
less than building the new runway (to say nothing of a new terminal and a new
people-mover), the poor-weather situation can be addressed, with very little
environmental damage.
The original approvals for the
third-runway project were based on cost-benefit work that is no longer
applicable, requiring a re-examination of the claimed 'need' for the Project,
and of the claimed benefits.
Each of the Project’s proponents has
given its own approval to the Proposal.
The Port has done so with a resolution of its Commissioners, with no
independent analysis. The FAA has done
so with its “Record of Decision” (ROD), which presented a page or two
recapitulating the previous undocumented claims of vast costs to airline and
travelers from ‘delay’ (not defined).
Subsequent facts challenge the current validity of that FAA approval.
Since the close of the comment period
on the original application, much new information about the dollar costs of the
third runway has come to light. First,
it has been revealed that at the time of the application, the Port did not have
enough cash in hand & grants promised to permit construction on a pay-as-you-go
basis. That meant that the Port would
have to borrow money to pay its contractors.
The funding shortfalls and the costs of borrowed money were never
alluded to in the EISes or the FAA’s ROD or the Port Commission’s
resolution. As of the time of the
earlier application, the cost of the runway was represented as being just over
$587 million. The Port had in hand cash
& grant commitments for just $180 million.
Second, we now have some real-world
figures for the cost of borrowing by the Port for this Project, because the
Port has now actually undertaken a partial borrowing for that purpose. In mid-1998, the Port issued long-term debt
secured by future passenger facility charges (PFCs), in part to acquire money
for third-runway purposes. On the basis of that application, RCAA performed a
simple calculation, comparing amount borrowed with amount to be repaid: the calculation shows that the Port must pay
out $3.23 for each dollar borrowed. Put
in other words, to find out how much the Port must repay, multiply the amount
borrowed by 323 percent. Only part of
the money from that PFCs-secured borrowing was intended for third-runway
use. The amount for that purpose was
$114 million; the amount to be repaid
on that sum was $369 million (principal, $114 million; interest & other
costs, $254 million). That additional
$254 million for interest &c., brought the cost of the Project to $841
million. But the borrowing still left a
shortfall of cash & other funding of $293 million.
Third, after the issuance of the PFC
bonds, it became feasible to make a fairly precise estimate of the total cost
of the Project, on the basis of the stated construction price of $587 million,
using the Port’s actual experience with its PFCs borrowing as a guide. The results of that calculation show that
the total unfunded $293 million in construction costs would turn into a
long-term obligation costing $959 million to retire, the original $293, and
another $657 million in interest & other costs. Thus, to buy a runway whose cost was estimated at $587 million,
the Port would actually pay out $ 1.499 billion! These numbers were not before the DOE when the previous
application was active. They suggest
that the cost-benefit analysis in the ROD was obsolete.
Fourth, the exercise of the PFCs
borrowing, together with a host of internal Port documents obtained in the last
few months, reveal that the Port is in a serious cash-flow bind as to its
capital-construction projects. This is
not a short-term deficit that can be met by short-term borrowing, or some
simple ‘tweak’ of revenues. No, the
shortfall is so great that hundreds of millions (more likely billions) must be
borrowed, & the terms of the borrowings must extend for decades. This is not just for the third runway, but
for the whole array of proposed construction projects, including the two most
closely associated with the runway -- the new terminal and the new 'people
mover'.
Fifth, in June 1999, the Port admitted
to another huge increase in the projected costs of the third runway. Staff’s June 1999 estimate was $773
million. We note that was a 31 percent
increase from the official figure of 18 months previous. The Port Commission voted to accept those
numbers.
Sixth, the new increase in costs of
construction necessarily implies an increase in the total outlay for costs of
borrowed money. No new grants, no new
cash, have come the Port’s way. The
Port’s financial position having not improved in the interval since the
PFC-backed borrowing took place, it is reasonable to suppose that the Port will
have to borrow against future revenues for a term similar to that of the first
PFCs bonds, & at a similar per dollar cost. No other scenario has been proposed. The additional construction costs of $286 million will require long-term
borrowing, which will lead to an ultimate payout of over $900 million
dollars. The true cost of the Project
now stands at something in the range of $2.1 to 2.2 billion. Contrast that figure with the $587 million
reported to the public and the DOE in late 1997, and one sees that all the
cost-benefit work needs to be re-figured.
One further needs to consider that with
no source of funding for the new shortfall in view, there is a very real risk
that if permission were granted for this project to go ahead, the project will
stall out, with the damage to wetlands accomplished but no runway constructed,
&, thus, no benefit however debatable conferred on the travelling public or
the airlines.
These new costs figures should impel
the DOE to conduct its own thorough, independent, & credible review of the
costs-benefit analysis, and of the ‘delay’ issue.
In conducting that analysis, the DOE
should bear in mind the point made in our discussion of project piecemealing, §
2.4 supra, -- in order to make the third
runway work as intended, the Port must also construct a new North Unit Terminal
(estimated to cost $468 million to $498 million as of December 1995), a new
people-mover for that new terminal ($75 to $150 million), & (though this
may be somewhat optional), a new parking structure to serve the new North Unit
Terminal, at a late-1995 cost of $60 million dollars. Just these three auxiliary projects were estimated (four
years ago) to cost a total of between $603 and 798 millions.[vi] And most of that sum must also be borrowed,
on the long term, with a big multiplier to capture the real cost, construction
price plus cost of borrowed money. And,
it should be borne in mind, the serious engineering on those supporting projects
has not begun, so the serious increases in the original estimates have not
begun either. Based on experience with
the runway itself, one would expect the early estimates for these components to
triple.
The costs of this Project will not
benefit those who pay them, a factor that should be borne in mind in assessing
'need'.
The issue of overall-cost, including
the cost of borrowed money, is separate from the issue of how the Port might
generate a revenue stream that would be an acceptable security for further bond
issues. May we assume that the DOE is
aware that financial institutions will not lend large sums of money (we’re
talking hundreds upon hundreds of millions here) without some form of security? For airports owned and operated by Port
districts in Washington, there are only a very few forms of security, all of
them future revenue streams, as follows:
Borne directly by the people of King
County
·
tax revenues,
·
future PFCs, &
·
miscellaneous and usually minor revenues from such Port
activities as parking garages, charges to concessionaires & non-airline
tenants, & other even more minor sources.
(We attribute PFCs and miscellaneous
revenues to the people of King County, because studies have shown that the bulk
– though not all -- of the travelers out of the Airport are residents of King
County.)
Borne directly by the airlines
·
revenue from airlines (normally under their Basic Airlines
Lease Agreement with the operator)
For cost-benefit purposes, the nature
of the revenue is irrelevant, so long as it is reasonably certain: the differences, if any, between interest
rates for bonds based on one revenue stream or another, will be relatively
trivial.
However, in terms of benefits to
airlines & to the travelling public, there is a real difference in how the
Project is funded. (There is no benefit
to the taxpayers of King County, as such: if the project is funded in whole or
part by tax revenues, taxpayers as such pay a direct price & gain nothing
in return. Federal statutes forbid the
Port from returning to the taxpaying public any part of the profit on its
airport operations.) The two alleged
purposes of this project are (1) to confer a direct benefit on travelers by
reducing their lost time while travelling to Sea-Tac, & (2) to confer a
benefit on commercial air carriers by reducing their operating expenses by
reducing operational time on flights to Sea-Tac. (Whether reduced costs to airlines would result in a reduction of
airfares charged to travelers is a question that seems not have occurred to FAA
and the Port – at least it is not referred to in their numerous volumes of
environmental review.)
If the Port were to rely on its tax
revenues, the funds would come out of the pockets of King County
taxpayers. To the extent that the Port
relied on PFCs & miscellaneous revenues, the burden would fall on users of
the airport – travelers, in the case of PFCs, and travelers & perhaps
others in the case of the miscellaneous revenues. If the Port were to rely on these revenues, airlines would
receive (per the Port’s numbers) very large economic benefits at the expense of
others. Air travelers & taxpayers
would buy the Project for the benefit of the airlines, in effect. Under this scenario, a true costs-benefit
study should be restricted to benefits to air travelers, the airlines not
having contributed.
The Port has repeatedly ruled out use
of tax revenues for third-runway purposes.
Its PFCs are already pledged to repay an existing bond issue, far into
the next century. (Even if the Congress
were to authorize an increase in the PFCs from $3 to $6, the amount of money
that could be raised thereby would be woefully insufficient to pay for the $7
to $10 billion in projected capital projects.)
We have yet to see any analysis that shows that parking fees and
surtaxes on espresso can pay for the Master Plan Update projects! This leaves a sharp increase in the BALA
rates as the sole revenue stream available to support the sort of major bond
issues required by the Project & associated construction.
Then the burden would fall in the first
instance on the airlines using the Airport.
It would be pure speculation to discuss how the airlines might
re-allocate those additional costs. Not
to the taxpayers of King County, surely, but perhaps to travelers from
Sea-Tac. And perhaps not.
There is an intermediate case: If
additional PFCs were used, airlines would argue that they would suffer a
diminution in revenue, on the generally-accepted premise that demand for air
travel is extraordinarily price sensitive, ‘elastic’ in economists’
jargon. The slightest change in airfare
is said to drive with rigidity a corresponding change in travel. (For the purposes of justifying the third
runway, the Port & FAA have advanced a different economic theory: they
argue that demand for air travel is completely inelastic. According to them, on this one occasion,
demand for air travel is in a direct, 1:1 proportion to overall economic
activity. Under this theory, the Port
can jack up its airline rentals to any level at all, the airlines will jack up
their ticket prices accordingly, & the travelling public will come in the
same numbers as always. This might be
true for governmental entities like the FAA and Port, but most corporate
controllers will not authorize big increases in travel expenses in budgets
already adopted. It is much more likely
that a big increase in airfare will lead to a sharp diminution in business air
travel to & from Seattle. Where is
the benefit for the scheduled airlines from such a development?
Further, if the airlines’ view of
airline economics is correct, as opposed to the governmental view, a diminution
in revenue occasioned by an increase in PFCs would eat into the economies of
scale that are essential for airline profitability. The Port and FAA have failed to present any analysis of whether
putative gains from faster arrival might not be eaten up by losses in
profitability resulting from decreased demand for travel.
In conducting its own review, Ecology
should be cognizant of the expressed opinion of several major airline users of
the Airport – this is not new information, but it is increasingly relevant as
the true costs of the Project, & additional information controverting the
notion of big delays, come to light.
Commenting adversely on the proposal to use new PFC charges for
third-runway purposes, airlines had the following to say:
·
"United
disputes the assertion that a third runway 'is necessary to eliminate a seven
minute average delay at the airport' and asserts that 'none of that delay is
attributable to the lack of the third runway, but a number of other
factors.' United is of the opinion that
'the airport's estimate that a third runway will provide $60 million of
operational savings is not supportable using standard business calculations.'
" [vii]
·
"TWA -- in
concert with Delta and United -- believes that extending the
Runway 16L-16R Safety area, 'instead of building a third runway -- is the best
alternative to address capacity issues caused by warm weather and Pacific
operations.' " (p.3,op.cit.)
Ecology should also be cognizant of the
results of a recent study done for National Aeronautical and Space
Administration (NASA) of major U.S. airports with parallel runways (including
Seattle).[viii] This study was not available to the public
or to the DOE before the close of the comment period on the earlier
application. The study was partly
funded by FAA (at the top level), & FAA did not register a dissent from its
conclusions. The study analyzed arrival
delays at the airports included in its scope.
What was the report on Sea-Tac?
“Arrival delay factors: None.” (p.48) May we suggest that a study done
for independent reasons for an outside agency necessarily has a lot more
credibility than a study done by a project proponent for the purpose of
justifying a project?
If, as RCAA has concluded (& NASA,
& several user airlines), there is no demonstrable ‘delay’, or if at the
most there is some delay, but not ‘delay’ that cannot be compensated for by
administrative measures, the certification should not granted, regardless of
conditions that might be imposed on it, for a showing of need will not have
been made.
If, as RCAA has concluded, the
cost-benefit analysis will not stand up in light of the newly revealed true
costs of the Project to the Port, the DOE should deny certification, for a
showing of need will not have been made.
The permit should be denied because of
the failure of the Application and the Proponents to provide adequate
mitigation of offsite impacts.
Some of those offsite impacts are obviously
environmental, & clearly within the purview of the Corps and Ecology:
impacts on Miller and Des Moines Creeks outside the Port’s acquisition area
(which includes most of the construction area). Those impacts include increased contaminants in the waters of the
Creeks from construction activities, & from continuation & expansion of
Airport activities upstream; silting & sedimentation downstream; flooding
downstream, with risks of bank erosions (& consequent loss of property
values), harm to stream-side natural habitat, harm to endangered species and
candidate species; release of contaminants & sedimentation into Puget
Sound. We will discuss these in detail
below.
Other offsite impacts are more
indirect, & for them no mitigation is proposed. Operation of a new runway will bring overflights of jet-engine
aircraft directly overhead in areas where there have not been such flights in
the past. This will result in new
adverse noise impacts, new air pollution (& consequent new water
contamination) from jet-engine exhausts, & a host of corollary negative
impacts. Until adequate mitigation is
proposed for these impacts (& until the public has had a reasonable
opportunity to comment on the mitigation proposals), the permit should be
denied.
To lend specificity to the foregoing,
we note that a prior independent study of potential adverse impacts from the
third runway (HOK Study) reported that every instructional building in the
Highline School District would likely need major noise insulation work, were a
third runway to become operational. The
cited study did not extend to the Seattle School District. However, a glance at the maps will show that
there are schools in the Seattle system as close to the new third-runway flight
corridors as the Highline schools, schools also likely to require serious
mitigation. Yet, the Applicant makes no
proposal to mitigate these impacts. The
silence of the Applicant on the question of third-runway impacts offsite should
require denial of the permit at this time.
1.
Will the Wall work?
An obviously critical part of the Port's plan for constructing the
runway embankment is the Wall to contain fill material where the embankment
makes its closest approach to Miller Creek.
The Wall is proposed in evident response to criticisms of the prior
proposal for essentially unsupported earthen fill. There is nothing before the public (see our comments infra, sec. 2.3 about the unsatisfactory
Public Notice) to show that the Wall has been brought to any appropriate state
of engineering. The information that
has come to the attention of RCAA as the result of diligent requests for
disclosure of public records and by virtue of the various informal
communications that have gone back and forth does not add any confidence that
the Wall will work. Appendix B to the
Impacts Analysis document cited in the Notice provides no details, only an
indication of various materials that are ordinarily used to build so-called MSE
walls. How any 'experts' can state with
assurance that the proposed construction will work, given the paucity of
information, is a mystery.
We are aware
of the existence of additional background documents for the Wall's
construction. The DOE should take
prompt, affirmative steps to put those documents into the public domain. (Ones that we know about are referenced in
section 2.3.13 infra.) Thereafter, the public should have ample
time to review those documents & to submit comments on them. These documents may contain the
missing, needful details of construction -- and maybe not! In the absence of the detail, the public
will conclude that the plan for the Wall is a plan for disaster. It will not do in this context for experts
hired by the Port to come in & say, in effect, "We are engineers and
we know best -- even if we don't what the actual method of construction might
be!"
2.
The Wall cannot be built without violating the standards for
construction in the protected (sensitive) areas. To construct the Wall, construction crews must work adjacent to
Miller Creek, and in wetlands. Damage
during construction will be difficult to remedy. The idea, floated at the public hearing, of building the wall
from the back, is hard to accept, & in the absence of any engineering
details seems utterly impossible. As
the plan is presented to the public at this time, it is self-evident that
construction of the Wall will result in serious environmental damage.
3.
Unstable soils. It
is well known that the soils in the construction area are of widely varying
quality, and that there is a serious risk that soils where the wall's footing
would rest are unsuitable for the purpose, and would need to be removed, to be
replaced by more suitable materials.
The notion of building the Wall from the inside out depends in part on
an unproven assumption that there are no unsuitable soils that would
need to be replaced. Yet Appendix B to
the draft Wetland Functional Assessment and Impact Analysis, at p. 24, concedes
that such soils do exist, posing a serious problem. "Existing soils in the area below the
Wetland 37 Wall, below portions of the embankment, and below portions of walls
in the North Safety Area, are unsuitable to support load of the new fill and/or
retaining wall." Ibid. Methods of removal & replacement of
these soils are then discussed -- though the document is silent as to
"overexcavation" would be performed, should the unsuitable soils
extend into Miller Creek, as may easily be the case.
It is good to
know that engineers know how to remove soil and to replace it, and firm up the
area for the planned work. But how does
this provide any assurance that use of these techniques will not result in
adverse impacts to Miller Creek, or that there is any sort of plan in place to
deal with those impacts when they occur?
It is
noteworthy that Appendix B warns that "[s]pecification of the final extent
and depth of overexcavation to remove unsuitable soils will require additional
explorations, which will need to include test trenches and test pits, to be
completed after construction access is permitted in the wetland areas to be
filled." (p.24, id..
In a nutshell, they don't yet know what they are doing or how damaging
it will be.
4.
Seismic hazards. The
lack of information about the planned method for constructing the Wall means
that there is a corresponding lack of information about the seismic hazards
that the Wall would face. Does Ecology,
will the public, accept the thoughts of a highway engineer from Georgia (where
there are no earthquakes) on the stability of a wall in earthquake
country? Where is the seismic analysis
of the proposed MSE wall that Ecology's engineer has recommended be performed?
[i] Parametrix, Inc.
August 1999. Wetland Functional Assessment and Impact Analysis. Master Plan
Update Improvements Seattle-Tacoma International Airport, Revised Draft
[ii] Parametrix, Inc. August 1999. Wetland Functional Assessment
and Impact Analysis. Master Plan Update Improvements Seattle-Tacoma
International Airport, Draft
[iii] Parametrix, Inc. July 1999. Wetland Functional Assessment
and Impact Analysis. Master Plan Update Improvements Seattle-Tacoma
International Airport, Draft
[iv] Sea-Tac
International Airport. November 1999. Wildlife Hazard Management Plan,
Seattle-Tacoma International Airport, Revised Draft
[v] Stockdale, Eric.
April 12, 1999. E-mail to Raymond Hellwig, Tom Luster re: Bird Strike Hazard
monitoring at SeaTac (Included with this submittal)
[vi] Port of Seattle,
January 1996, "Technical Report No. 8, Master Plan Update Final
Report", prepared by P&D Aviation.
[vii] Port of Seattle,
February 1998, "Passenger Facility Charge Application – Summary of
substantive comment by air carriers", October, 26, 1997,Tab C, p.6
[viii] NASA, May 1998,
"Air Traffic and Operational Data on Selected U.S. Airports With Parallel
Runways", prepared for Langley Research Center under Contract NAS1-96014
and for the Federal Aviation Administration under Contract DTFA01-97-C-00057.
Document no. NASA/CR-1998-207675 (Included with this submittal)
Cont'd. in Part 5