|
Chronology
of Section 401 permit, Second Application
29
September 1999. The Port submitted its second application
to the U.S. Army Corps of Engineers and to the Department
of Ecology, after having to withdraw its 1997 application
because of gross under-statement of the amount of wetlands
involved. Ecology had 365 days to pass on the application.
The Engineers had previously announced that they would not
decide till after Ecology had finished its work.
Spring & Summer 2000. Port of Seattle submitted
voluminous revised documents, attempting to justify the
plan, some as late as late August. Ecology, Engineers, and
King County stormwater experts, as well as experts retained
by Airport Communities Coalition, RCAA, and C.A.S.E., raised
a host of questions.
28 September 2000. A meetingnot publicly announcedwas
held at the office of M.R. ("Mic") Dinsmore, Executive
Director of the Port of Seattle. Those present included:
Joe Dear, the Governor's Chief of Staff; Mr Dinsmore; Tom
Fitzsimmons, the Director of the Department of Ecology;
Ray Hellwig, head of the regional office of Ecology; and
others. Mr Dinsmore was a major fund-raiser for Gov. Gary
Locke in the last general election. The Governor and Ecology
have denied that there is any political pressure in this
affair, though Ecology has been officially warned that there
is interest in this project "at the highest levels"
of State government.
The Ecology folks brought with them their draft letter of
decision on the sec. 401 application, dated that day, and
shared it with the others. The letter flatly denied the
application, because of multiple shortcomings. "At
this time, Ecology does not have reasonable assurance the
proposed project will comply with the applicable federal
and state water quality requirements
." The
letter referred questions to Ecology staffer Tom Luster.
The letter acknowledged that the Port intended to resubmit,
and pledged to "work with" the Port, and to "provide
guidance to the applicant to help develop documents with
the necessary level of detail and information for our review."
What else happened next at that meeting is not known.
However on that same day (28 September), the Port announced
that it was withdrawing its applications under sec. 401
and sec. 404 of the federal Clean Water Act. In a letter
dated that day to the U.S. Army Corps of Engineers, the
Port wrote that it was withdrawing "solely for a technical
reason, i.e., to grant Ecology additional time to complete
its review". In fact, the Port withdrew because Ecology
was poised to deny the application.
Also on 28 September, the Port issued a news release stating
it would resubmit in two weeks and asserting that the new
application would sail through to approval in a very few
weeks, by December at the latest. Curt Hart, public-relations
man at the Bellevue office of Ecology, said in a prepared
statement that the Port was "on the right track, conceptually".
Mr Fitzsimmons issued a letter dated that day to Mr Dinsmore,
in response to the withdrawal, saying that there was not
"adequate time to properly review ... remaining project
related issues", but he was "confident" that
Ecology would approve a renewed application. At the meeting
in Mr Dinsmore's office, the tentative timetable was, a
third application filed on 16 October, and a cut-off of
public comment by 30 November, with a decision in mid-December.
* * * * *
After the application was withdrawn, and while no new application
was pending, there were "negotiations" under the
chairmanship of a "facilitator" (Ms Kate Snyder)
from the firm of Floyd & Snyder, Inc. Putting a "facilitator"
in charge was one of the items discussed at the private
28 September meeting.
E-mail-traffic shows the following.
2 October. Meeting of Port, "facilitator",
and Ecology, to negotiate.
6 October. Ditto
10 October. Ditto. Two persons present from King
County, and six consultants, as well as Port and Ecology
folks.
13 October. Another "negotiating" meeting.
13 October. Curt Hart, the PR man, e-mailed an East-Coast
journalist that "we hope to have the permit issue resolved
by mid-December", and that the Port would not be required
to start over from scratch.
20 October. More "negotiating".
24 October. Technical stormwater plan status conference
(limited attendance, excluding Ecology)
DATE Ecology's Ray Hellwig wrote to RCAA that there would
be a new public notice and a new public hearing
27 October. All-day conference at Ecology's Bellevue
office
31 October. Another all-day meeting at Ecology.
None of these eight meetings in October were announced publicly
and no-one representing outside parties was present. The
public would not know that they occurred but for persistent
requests for disclosure of public records by ACC.
*
* * * * *
26
October. The Port filed portions of a new application,
announces the filing to the news media.
During October. The Corps of Engineers reviewed the
submission for Ecology.
3 November. Ecology started to withhold documents
sought by public disclosure on the grounds that they are
deliberative documents.
|