|
The decision yesterday from U.S.
District Court Judge Barbara Rothstein, denying the appeal
of the wetlands-filling
permit for the third runway, reminds us again of what judges
do, and what they do not and cannot do. And the decision
reminds us, again, of the serious flaws in the way that
proposals for big, expensive, damaging, public-works proposals
are handled.
The judges are NOT asked to "approve" projects,
such as the third runway. No doubt, the Port of Seattle
will say that Judge Rothstein “approved” it, but she did
not. The courts are NOT planning agencies – which is probably
a very good thing. Whether a project is a good one or a
bad one is never the issue in lawsuits such as the one
decided yesterday – the issue is whether the permit-granting
official or the planning agency has considered everything
required of it & used the right legal standards. Put
very simply, the question is, Has the agency (in this case,
the local office of the Army Engineers) done its paperwork
right? Unfortunately, the courts almost never approach
that issue independently -- they start with the presumption
that the agency HAS done its paperwork correctly.
In the sec. 404 case, the court
deferred to the supposed expertise of the Engineers (who
admitted that they had
never handled such a complex project). The Engineers in
turn deferred on various issues to the “expertise” of the
Port of Seattle (project sponsor), or the “expertise” of
the local FAA (project co-sponsor), or of the Department
of Ecology. Ecology of course had already been overruled
by the next level of higher authority, the Pollution Control
Hearings Board, on 16 important points. Ecology at various
stages along the way deferred to the opinions of the Port
and the FAA.
No-one conducted a genuinely independent
review of the project over-all. No-one conducted a genuinely independent
review of the environmental impacts. One agency (the PCHB)
undertook a genuinely independent review of the water-quality
impacts – and ruled against the Port and against Ecology,
as noted above, on 16 important points. [[ link to PCHB
order, earlier story / ies ]]
The Power To Say “No”
In fact, there is no independent
official or agency with the power to review these big,
damaging publicly funded
projects on their merits and to say “No” if need be.
Someone with a project to sell
is responsible for writing the environmental impact statement
for that project. Specialist
agencies may comment on particular aspects of an EIS – whether
the nesting grounds of spotted owls are at risk, perhaps. But
no-one is in charge of a complete outside review. Such
a thing does not exist. The project sponsor decides what
alternatives to consider in the EIS, & only those that
it selects are considered. In fact, in the case of the
third runway, the courts have ruled that the only alternatives
that need be considered are ones that the Port of Seattle
itself is willing to undertake! The project proponent may
be asked to prepare a costs-benefits analysis, but that’s
not a requirement of the State Environmental Protection
Act or its federal equivalent. If the numbers in a costs-benefit
analysis don’t pencil out, then the sponsor talks about
intangible benefits (while ignoring “intangible” costs) – and
according to Judge Rothstein, intangible benefits are enough
to justify a project that might otherwise not amount to
a public benefit.
With no-one except the project sponsor actually in charge,
the justification for a project like the third runway is
whatever the sponsor (in this case, Port of Seattle) chooses
to say at the moment.
If One Story Doesn’t Work,
Try Another
Originally, the third runway was
sold as a project to enhance capacity at Sea-Tac–-to
bring in more planes & more
passengers. That turned out not to be the case. So then
the “reason” was to cure delay–-at an airport with a one
percent delay factor. Well, it’s delay in peak travel periods
with bad weather. Well, Sea-Tac’s peak period is August – where’s
the bad weather? No answer. How many flights are actually
delayed? No answer. Then the excuse became the dollar cost
of delay, which of course was vastly exaggerated. And when
would that delay occur? Some time in the far future. When?
Hard to say, for not one of the official projections of
future travel demand at Sea-Tac has ever been right, or
even close to right.
Then at the Legislature this spring
the runway became a jobs program (short-term work assignments
for a few hundred
Teamsters). That got laughed down. So now, we read in Judge
Rothstein’s opinion, the Port has turned to “intangible
benefits”, which cannot be quantified–- and the Engineers
should defer to the Port’s judgement about the importance
of those “intangibles”, & the court should defer to
the Engineers’ deferral to the Port. And suddenly, it’s
also a safety measure (a case never proven, & in fact
never seriously examined in any of the dozens of documents
that have come our way). And–-another intangible benefit,
another afterthought–-it’s a question of making travelers
feel good about air travel. Obviously, this is all nonsense,
but there’s no-one who has the right to say, “This is a
bad project, & it has to stop”-– no-one except the
Port Commissioners, & certainly NOT the judges.
Under the present system, huge
airport projects like the third-runway get the OK of
a regional FAA office, but are
not approved at the central headquarters at any level,
not by the Administrator of the FAA, to say nothing of
review by a Cabinet-level officer. Yet, that same regional
FAA office is also a sponsor of the project. In many cases,
a regional FAA office is the outfit that initially suggests
a particular airport project to an airport operator. It
then works with the airport to develop the plans, & to
prepare the EIS, & then it reviews the project for
an FAA OK, & for federal grants!
Until this lop-sided system is
fixed, we will continue to see unending controversy over
public-works projects,
especially those with dubious benefits, huge ongoing impacts
on people’s daily lives, out-of-control budgets & voo-doo
financing, grave potential for environmental harm in the
immediate vicinity, and almost total lack of mitigation.
The courts do not have the tools to fix this mess. Lawsuits
can only chip away at the fringes of the problem, seeking
to require project proponents & their partners in permitting
agencies to re-do work that is overly slipshod. The courts
do not have the power simply to say “No”. That’s up to
the public.
|