June 27, 2003

Port Staff to Commissioners:
"We Blame the Neighbors"

The Port staff were quick to claim at the Commission meeting on 24 June that opponents & critics of the third-runway project at Sea-Tac Airport had caused vast delays in the Port’s construction schedule with their lawsuits, thus running costs up a couple of hundred million dollars. (If you have bad news, try to change the subject.) The Commissioners acted outraged, blaming the neighbors as well.

The overrun estimate included $55 million itemized as caused by “delay” of the project. This supposedly includes $20 million attributable to inflation (not otherwise described). What items were delayed? Unknown. For how long were they delayed? Unstated. How much were those items supposed to cost originally, & what will they cost—or have they already been purchased? Unknown.

The “delay” item, according to Mr. David Soike, Director of Capital Improvement Program, also included additional environmental & legal work, details unstated. It would be more accurate to say that staff simply underestimated the requirements in these areas. This is not a delay matter but a lack of foresight. It was unwise to suppose that this project would not be challenged, would not be subjected to very careful review.

The other $151 million blamed on the neighbors by the Port was for "additional environmental permit requirements." The basic source of this overrun was a decision to ignore real environmental impacts in their planning or to budget realistically for them. The biggest and most costly example was the staff's decision to ignore their own consultant's advice that there could be 100 acres of wetlands on the runway site and to plan, instead, for 10 acres and to estimate their costs accordingly.

The simple fact is that despite the risk of losing lawsuits or not obtaining permits, the Port has pursued the runway project full bore, with no delays from the courts, ever since planning for the runway began in the late 1980s. There has never been a court order stopping planning, designing, or construction, until the temporary injunction entered in December 2002 by the local U.S. District Court—and the Port agreed to that order being issued!

Runway Work Proceeded Throughout the 1990s

Opponents of Sea−Tac expansion were arguing in the 1990s that planning approval should not be granted, & when it was granted, they challenged those actions in court. While the courts were considering such issues as whether the environmental impact statements were adequate, and whether the requirements of the Growth Management Act were met, the Port went forward with in-house design work, & then awarded engineering contracts to outside consultants. The Port obtained authority from the City of SeaTac to issue city building permits to itself for the project. The Port decided what properties it needed to obtain for the runway, & went forward with negotiations & condemnation actions, till all the land was acquired. The suits against the runway did not affect any part of this work.

When enough land had been acquired, the Port began contracting with construction outfits for delivery of fill for the runway embankment. The Port also began to remove fill for the purpose from other parts of the Airport. This process went on for five years without challenge in the courts, & only stopped when the Port ran out of space. About five million cubic yards were laid down—about a quarter of the total fill needed (19.84 million cubic yards).

Wetlands Permits—An afterthought?

Well into this fill-hauling work, the Port got around to seeking permission to fill wetlands, alter watercourses, & do other runway-construction work needing the OK of the State Department of Ecology and the U.S. Army Corps of Engineers, under the provisions of the federal Clean Water Act of 1972 and companion legislation at the State level. These laws require that the applicants (Port) take appropriate measures to mitigate the environmental harm of their projects.

The Engineers and Ecology were made aware of the ongoing fill work, and Colonel Mike Rigsby, in charge of the local office of the Engineers, publicly warned the Port at a hearing on 3 November 1999 that they were “proceeding at their own risk” in moving large quantities of fill without any assurance that a permit would be granted. The Port went ahead anyway.

Bad Plans, No Permit

The Port staff & consultants presented seriously inadequate plans to Ecology & the Engineers. The plans short-changed mitigation & were full of factual errors. Runway opponents, in the form of the Airport Communities Coalition, critiqued the Port plans in great detail, providing expert advice & comment to the Engineers and Ecology, and thus, indirectly to the Port. The two agencies met time without number with Port staff & consultants, trying to bring the plans into legal compliance.

The first application was granted by Ecology, appealed to the Pollution Control Hearings Board, and then the approval was withdrawn.

A second application followed, again with public hearings, lots of comments from the public & from ACC experts & others. Again, the Port could not put together a suitable plan, & in mid-1999 was told by Ecology that if they did not pull the application & start again, it would be publicly denied. The Port withdrew & re-submitted. They expected to finish their work & to receive their permits by December 1999, if not sooner. The Port continued with construction of the runway embankment as planned—with no environmental permits in hand.

Third Time’s the Charm

On their third try, the Port & its consultants radically revised their plans, adding very expensive new features, & after prolonged discussion, Ecology issued its approval, with strong conditions, in August 2001. An appeal followed, & a three-week trial then took place before the state’s Pollution Control Hearings Board in March 2002―the first public review of the environmental plans. In August 2002, the Board upheld the certificate, with 16 more conditions added to ensure that the project did not violate state water law. The Port has since appealed eight of those conditions to the courts.

In December 2002, after further study, the Engineers gave their approval, & that is now under review in the U.S. District Court. The Port agreed to an order in the federal court that they would not do work in the wetlands pending the final result of the court case (though they have the right to withdraw from that order if they wish).

Port Set Schedule from the Start

The Port was in complete control of the timing of its work from the very beginning. The Port decided when to seek the necessary concurrence of the metropolitan planning organization (Puget Sound Regional Council). The Port decided when to ask the FAA for its planning concurrence. The Port decided when to ask FAA for a construction-money grant. The Port alone decided when to borrow construction money on Wall Street, when to ask approval to use passenger landing fees for runway work, when to start working on a new lease arrangement with the tenant airlines, when to impose a tax increase for runway money, & most important of all, the Port and the Port alone decided when to start hauling fill & when to ask the environmental authorities for the right to fill wetlands.

Legal Delays Began in 2001

The Port proceeded in fits and starts, depending on how much money it had available and how far along it was in the planning process until the year 2001. They hit a legal roadblock then. That’s when they needed to put new fill into wetlands but did not have their permit—because of their own failure to do their environmental work as the law requires. They tried to cut corners, & it did not work. Now they are in a mess. Port staff & Commissioners are claiming that it was a bad thing for outsiders to call attention to the Port’s serious errors & omissions. But the simple truth is, if the Port had done its work correctly, its wetland permits would have been received years ago. No court, no lawsuit, created the problems with the environmental permits―the Port created these problems itself.

What About Changing Laws?

There has been loose talk from the Commissioners & from the Port’s spinmeisters that the Port was sandbagged by ever-changing environmental laws. At the meeting on the 24th, particular complaint was made about the Endangered Species Act (a new theme in the Port’s litany of woe, by the way).

This is all nonsense. The applicable statute as to water quality (wetlands) is the federal Clean Water Act of 1972. The Endangered Species Act has been on the books since 1973. Does the Port claim that it started planning the runway way earlier than 1972?  That was before the second runway opened for business. The law is unchanged. The standards are unchanged. It’s up to project proponents like the Port to present plans that meet the legal requirements. People who don’t want to comply with the law, people who present shabby plans, people who propose stupid projects in stupid places, make trouble for themselves.

The staff told the Commission that the project has had big delays because of community opposition through lawsuits. Actually, the project has proceeded as planned until quite recently, when the Port failed to submit adequate plans for control of water pollution & mitigation of damage to wetlands, something that they could have avoided had they taken the wetlands problem seriously in the first place.

 

 


©RCAA 2003
Regional Commission on Airport Affairs
is a nonprofit citizens' organization
19900 4th Ave S.
Normandy Park, WA 98166
(206)824-3120

E-mail us

 
   

related stories, see links below

Seattle P-I
Seattle Times (Editorial
)