2002,
The Year the Trucks
Stopped Rolling
Summary
The
runway battle in the year 2002 was largely about the inability
of the Port of Seattle to find a way to design and build
the runway without violating State or Federal environmental
law. The Port still does not know how to do that, which
is why there has been no serious runway construction since
2001.
The
Port needed to get two key environmental permits in order
to fill wetlands and relocate streams in the area where
the new runway would be built. It got the first permit in
2001, but the Airport Communities Coalition (ACC) appealed
it to the Pollution Control Hearings Board (PCHB). The Board
issued a stay in January, held hearings in March, and ruled
in August. The Board granted the permit, but with
a list of conditions. The Port appealed, claiming it couldn’t
build the runway if required to comply with the conditions.
The
second permit was the responsibility of US The Army Corps
of Engineers Seattle District. In December, the Corps issued
the permit, incorporating some of the PCHB’s restrictions
but not all of them. The ACC appealed on the grounds that
the Corps was required to incorporate all of the restrictions.
As
of now, everything is in the courts on appeal. In the meantime,
the Port cannot legally move fill for the runway, so the
trucks cannot roll.
The
other big event in 2002 was in April, when the Port and
the Highline School District finally reached agreement on
a $200 million noise mitigation package in Highline schools
for damage done by the second runway, built in 1972.
Things
that did not happen in 2002,
but should have...
Again,
the Port failed to reconcile its claims of serious delay
problems with a national study by the FAA in 2001, showing
that only one percent of arriving flights at Sea-Tac were
delayed by local conditions––well under the threshold of
concern to the FAA.
The
Port failed for the third year running to issue a revised
cost estimate for the third-runway project or a plan for
raising the needed money. The last estimate was released
in June 1999 before the 150’ high rammed earth wall (the
“great wall of Sea–Tac”) and many other items were added
to the plan. Our best estimate of construction costs is
a billion or more––and the Port apparently has little money
on hand to pursue future work.
The
Port’s National Discharge Elimination Permit (NPDES)––the
permit that allows it to discharge any pollution––expired
and a new permit with more stringent pollution controls
was supposed to be issued by the Department of Ecology.
So far, no permit. The Port is living on a temporary extension.
As of now, the rumor is that a draft for public comment
may be issued in the second week of February.
2002 In Review
January
Pollution
Controls Hearings Board Issues a Stay: On the 9th,
the state Pollution Control Hearings Board issued a stay
of the Section 401 certificate previously issued by the
Department of Ecology for runway construction work in wetlands
and streams. The stay meant that until the Board issued
its final ruling, the Airport could not fill wetlands or
relocate streams––all part of the runway project. The Board
cited the "likelihood of success of the merits of the
appeal" of the permit by the Airport Communities Coalition
(ACC). The permit was issued by the State Department of
Ecology in 2001, and appealed to the Pollution Control Hearings
Board by ACC.
The
stay order was a huge win for the no-runway campaign. This
was the first time that a truly independent reviewing agency
had looked at any part of the project on the merits––and
their first impression was that the Port’s plans didn’t
meet the legal requirements.
The
Port immediately appealed the stay to Thurston County Superior
Court (but in the end, nothing came of that).
Port
asks for bids on wetlands work without a permit:
Also in January, the Port advertised for bids for runway-related
work in local wetlands, including relocation of Miller Creek––for
which the Port did not have the required permit from the
U.S. Army Corps of Engineers, as required by sec. 404 of
the federal Clean Water Act.
February
Port advertises
for fill bids: In February, the Port advertised for
bids for the major third-runway work for the year. The major
item was addition of about 2.5 million cubic yards of fill
to the existing piles of fill. Two million cubic yards were
to come from off-Airport, and half-a-million from other
parts of the Airport. The Port expected the bids to range
between $30 and $45 million. The ad warned prospective bidders
that the Port did not have its Corps of Engineers permit,
and that its OK from Ecology was on appeal.
March
Pollution
Control Hearings Board holds hearing on “Section 401 Permit”:
Starting with a three-week hearing before the Pollution
Control Hearings Board in March on the Airport Communities
Coalition (ACC) challenge of the Port "section 401
certificate", people in the airport communities learned
more about the Federal Clean Water Act than they ever imagined
they would. The hearings board heard in great detail about
unresolved environmental problems in the third-runway plan.
(See the Wetlands Section of our on-line library for copies
of many of the submissions from experts.) The stay remained
in effect.
Highline
passes school bond issues: In March, Highline voters
passed a $189.5 million bond issue for their schools, with
$50 million earmarked for noise-insulation projects.
April
Port funds
school noise agreement. On April 24, the Port of
Seattle Commissioners voted to authorize the money to fund
a plan to mitigate second-runway noise in the Highline schools.
The Port of Seattle, the FAA, the State, and the school
district had agreed in principle to provide $50 million
each for a ten-year, $200 million package of noise-reduction
remedies. Over half of Highline School District schools
would benefit. The second runway opened for business in
1972.
Port
cancels bids for wetlands work: On 20 April, the
Port cancelled its earlier requests for bids for wetlands
work and for runway construction. This work has not been
re-advertised, and not a spoonful of runway fill has been
brought in to the site from off-Airport sites from then
till now. The trucks stopped rolling and remain stopped.
June
Old
Port National Discharge Elimination (NPDES) Permit continued
temporarily: The date for renewal of the
Port’s five-year water-pollution, or NPDES, permit for the
Airport came and went. The Port’s proposal for the renewal
was not acceptable to Ecology, which was working on its
own, much more stringent version. The old permit was continued
in effect temporarily.
August
PCHB
imposes conditions on Section 401 permit, and Port appeals:
On the 12th, the Pollution Control Hearings Board
released its final decision. The Board agreed that the Port
should get a sec. 401 certificate––under new and much more
stringent conditions. The Port appealed the decision, stating
that the conditions imposed by the Board claimed would prevent
it from building the runway. This was the second big win
of the year for the no-third-runway campaign.
Highline
Schools Noise Mitigation:
On the 24th & 25th, Highline School District,
the Port of Seattle, the FAA, and the State signed the final
agreement on the $200 million noise mitigation plan.
September
Ecology fails to
release draft NPDES permit. Ecology was supposed
to, but did not, release the draft of the new NPDES permit
for the Airport. Discussions with the Port did not resolve
disagreements over the new, tough conditions that Ecology
wanted.
December
Army Corps issues
section 404 permit, and ACC appeals. The U.S. Army
Corps of Engineers at last completed its part of the environmental-approval
process for runway work, by issuing a sec. 404 permit for
wetlands and stream work. Some but not all of the stringent
conditions required by the Pollution Control Hearings Board
were included. The ACC immediately appealed to U.S District
Court, and on the same day, the District Court temporarily
enjoined any work under the permit.
No
NPDES Permit: Again, Ecology was unable to release
a draft of the new NPDES permit for the Airport.
|