|
Runway
costs exceed $342,000,000
total
budget figures unknown
As of the end of May, the Port of Seattle had spent more
than $342 million on its third-runway project at Sea-Tac
Airport. According to the RCAA, this amounts to a huge gamble
with taxpayers' money, because the Port has no guarantee
that it will be allowed to proceed to completion.
As shown by Port financial documents, the runway costs fall
into several major categories. The biggest expense so far
has been for purchase and condemnation of property. The
site for the proposed runway is outside of the pre-existing
western boundary of the Airport, so some $158 million has
been spent to increase the Airport's area. Port planners
are eyeing additional property at the north end of the Airport,
in the City of Burien.
The next biggest expense has been for construction of the
actual runway embankment, including $67 million just to
buy fill, and more than $23 million in other expenses. This
is only the beginning, according to Port figures; the total
embankment budget is presently set at $350 million.
Another major expense category is building taxiways, to
connect the proposed runway to the pre-existing Airport:
this work, costing $48 million, is essentially complete.
Reported legal and administrative expenses exceed $15 million.
Engineering and design expenses, in the millions, are scattered
under numerous budget categories.
These expenses are detailed in monthly summaries of expenses,
released by the Port in July.
The most recent official estimate for total project cost
is $773 million, but that figure was released more than
three years ago. Since then, Port staff have been quoted
as saying that new environmental-mitigation projects would
cost another $200 million. In the monthly expense summaries,
only $2 million is earmarked for mitigation. The Port claims
that there is no up-to-date estimate for the whole project.
"These documents show that the Port is taking a shocking
gamble with the public's money," commented Larry Corvari,
President of the Regional Commission on Airport Affairs.
Mr Corvari added, "Col. Mike Rigsby, head of the Seattle
Office of the Army Corps of Engineers, warned Port officials
back on November 3rd, 1999 that they would be "proceeding
at their own risk", if they started construction without
the wetlands permit required by section 404 of the Clean
Water Act. Now we learn that nearly $350 million has been
spent, with no permit. If the Port doesn't have a Plan B,
that money may be down the rat hole."
Stuart Creighton, a member of the executive committee of
the Airport Communities Coalition, said "These numbers
are shocking, but not surprising. Other airports are able
to build full-service, 10,000-foot runways for less than
the Port has spent just in buying property for this 8,500-foot
part-time runway. Trying to build a runway by piling 20
million cubic yards of fill on the side of a hill just doesn't
make sense. Trying to do this in an area full of creeks,
wetlands, and ponds makes even less sense."
|
|