http://www.rcaanews.org/rcaa
Comments of the Regional Commission on Airport Affairs (RCAA) on the Draft Supplemental EIS (dSEIS) to the Seattle-Tacoma International Airport Master Plan Update
http://www.rcaanews.org/rcaaseis.htm
Comments of the Regional Commission on Airport Affairs
(RCAA) on the Draft Supplemental EIS (dSEIS) to the
Seattle-Tacoma International Airport Master Plan Update
[Editor's Note: Comments on the Port/FAA Draft SEIS
must be received by the FAA no later than March 31,
1997. Mail comments to:
Mr. Dennis Ossenkop
Federal Aviation Administration
Northwest Mountain Region
1601 Lind Avenue Southwest
Renton, WA 98033-4056
Also, please mail a copy of your comments to RCAA at 19900 4th Avenue SW
Normandy Park, WA 98166
Your questions and comments must be specific. Otherwise the Port/FAA may
disregard them and claim they are too broad. Ask that the agency comply with the
requirements of Section 1503.4(5) of the National Environmental Policy Act
(NEPA) which requires that the responding agency.
"Explain why the comments do not warrant further agency response, citing the sources,
authorities, or reasons which support the agency's position and, if appropriate, indicate
those circumstances which would trigger agency reappraisal of further response."
---------------------------------------------------------------------------------------------------------------
PREFACE TO COMMENTS
The Regional Commission on Airport Affairs (RCAA), a Washington corporation,
is a non-governmental, citizen's organization, whose mission is to achieve a long-term
integrated plan for air and surface transportation to meet the competitive needs of
Washington state, and to achieve immediate and permanent reduction in noise and other
adverse environmental impacts from commercial aircraft in the Puget Sound Region.
RCAA is governed by its Board of Directors, with input from numerous volunteers
and from endorsing and supporting organizations in Pierce and King Counties. Its work is
primarily performed by its volunteers. RCAA was created to be, and is, a coordinating and
'umbrella' organization for citizen groups, institutions, organizations public and private, and
individuals who support its mission statement.
Since its founding, RCAA has closely followed and actively participated, to the
extent permitted, in such processes as the Port-PSRC Flight Plan study, the work of the
State Air Transportation Commission, the work of the State High-Speed Rail Commission,
the Expert Arbitration Panel review ordered by PSRC, and the present environmental
review for the site specific third-runway proposal. Representatives of the organization have
spoken and testified at numerous public hearings, have submitted their own studies and
critiques, have encouraged others in similar activities. RCAA has commissioned expert
studies of particular issues and has submitted those studies to appropriate official bodies
involved in airport and transportation issues.
RCAA submitted extensive scoping comments at the start of the present
environmental review and participated in the one occasion afforded for public input during
the scoping process. RCAA's preparation and submission of the following comments on
the Draft Supplemental Environmental Impact Statement for the Sea-Tac International
Airport Master Plan Update is part of its ongoing concern with transportation issues and
the adverse impacts of commercial aviation activities.
Introduction to comments of RCAA on the
draft Supplemental EIS for Master Plan Update
A note on method: With stated exceptions, the abbreviations used in these comments
are the same as those used in the draft Supplemental Environmental Impact Statement.
Exceptions: 'POS' is sometimes used to mean 'Port of Seattle'; 'dSEIS" is used to refer to
the draft Supplemental Environmental Impact Statement (the subject of these comments);
'fSEIS' is used to refer to the final Supplemental Environmental Impact Statement to be
issued in due course.
Our comments are numbered sequentially within each of the following categories, each
of which includes discussion of related mitigation issues:
1. Construction Impacts (see dSEIS sec. 5-4)
2. Air Quality (see dSEIS sec. 5-2)
3. Noise (see dSEIS sec. 5-3)
4. Wetland and Water Quality Impacts (see dSEIS sec. 5-5)
5. Social and Socio-economic Impacts (see dSEIS sec. 5-7)
6. Alternatives (see dSEIS sec. 1-3, Chap. 3)
7. Other Comments
(A) Planning Horizons
(B) Surface Traffic
(C) Cost
(D) Methodological Concerns
(E) Miscellaneous
8. Request for Extension of Time to Provide Additional Comments
General Comments: We noted in our General Comments to the original draft EIS
that the environmental consequences of the project are grossly understated, & that
mitigation measures are utterly inadequate. Passage of time, and independent studies by
disinterested experts (the Burien Impact Study team, for example), have only strengthened
those conclusions.
Like its predecessors the DEIS and the FEIS, on almost every topic examined in which
serious impacts on the surrounding communities are involved, the dSEIS does not meet
minimum standards for accuracy, fairness, completeness, or technical competence. Major
conclusions are stated as bald matters of fact, without citation to authorities. Important past
& pending studies are omitted, and not even referenced. Permit applications submitted by
the Port, and relevant reports and plans prepared by, or for, the Port are not mentioned.
Documents are incorporated by reference under circumstances such that almost no
readers could possibly become familiar with those documents (which, by the way, is a
practice that we believe to be unlawful).
Concerns raised by us in our original scoping comments, and again in our comments
to the DEIS, continue to be ignored. A clear example is our repeated request that
projections not be expressed in terms of one absolute figure, but that ranges be presented,
with analysis of probabilities. Yet throughout the dSEIS the reader finds projections
expressed as single numbers when it is patently obvious that no reasonable person would
stand behind such rigid projections. Issuing projections in the dSEIS without explaining
their level of uncertainty is both unprofessional and misleading.
Finally, we believe it is vitally important that the Final SEIS detail the commitments
which the Port/FAA has provided to local cities, communities and residents to mitigate the
impacts of the options proposed in the dSEIS. The mitigation promised by the Port of
Seattle associated with its 2nd Sea-Tac runway expansion was not provided as promised.
The impacts of this unmitigated damage have not been forgotten in these communities.
We therefore believe that, prior to proceeding with discussions of any of the alternatives
described in the Draft SEIS, the Port of Seattle/FAA should enter into binding agreements
with local municipalities which dictate specific terms of how the impacts of the proposed
actions will be compensated, and the mechanisms and means through which these
programs will be accomplished in the affected communities and cities.
RCAA COMMENTS ON DRAFT SUPPLEMENTAL IMPACT STATEMENT
PART 1: CONSTRUCTION IMPACTS
1-1. Truck Trips -- How Many? The discussion of truck trips for hauling fill
material, found at p. 1-10 of the Summary, is unclear. Will the number of hauls and
length of day during which loads are hauled be reduced? or not? The summary in
the fSEIS should be clearer.
1-2. Truck Trips -- How Many? P. 5-4-4, first unnumbered paragraph, second
sentence, refers to '109 hourly truck trips on all roads'. Compare to footnote 1, p. 5-
4-1, which seems to refer to 109 trips per day. Is it contemplated that there might be
as many as 109 truck trips per day or 109 truck trips per hour? (The per-hour
interpretation of-these ambiguities is strengthened by the reference to 1109 one-way
peak hour truck trips' in the last full paragraph at p. 5-4-7.)
1-3. Truck Trips -- How Many? A table or graph might usefully be inserted in
section 5-6 (A), showing anticipated numbers of trips per day for representative
dates during the 5-year fill-haul period.
1-4. Truck Trips -- How Many? A table or graph might usefully be inserted in
section 5-6 (A), showing anticipated numbers of trips per hour at the same dates
used in constructing the table for trips per day suggested in the immediately
preceding comment.
1-5. Truck Trips -- How Many? At p. 5-4-1, do the numbers in footnote 1 refer
to daily trips? If so, the note needs to state that clearly.
1-6. Truck Trips -- Is It Trucks Only? The discussion of fill-hauling in the
Summary, at p. 1-10, is couched in terms of truck trips. Is it not intended to use
truck-trailer combinations for fill-hauling, & is not the discussion of numbers of trips,
hours of operations, number of years needed for fill-hauling, all predicated on using
truck trailer combinations?
1-7. Noise from Fill-Hauling. The Summary (p. 1-10) is silent as to any noise
impacts from the fill-hauling operations. Surely some noise impacts are expected?
The fSEIS should discuss this matter in the Summary.
1-8. Truck Trip Scheduling. Why will the fill-haul work peak at any particular
year, and why the year 2000? (See sec. 5-4 (A), p. 5-4-2, second numbered item
under first bullet point.)
1-9. Tables Need Work. The table numbering in section 5-4 needs to be
changed in the fSEIS, to include numbering of the unnumbered table now appearing
on p. 5-4-3, which should be Table 5-4-1, & then renumbering all further tables in the
order in which they appear. It is confusing, & inappropriate, to have Tables 5-4-6 &
5-4-7 appear before Table 5-4-1, especially when no page numbers are provided
when the tables are discussed in the text.
1-10. Construction Noise Impacts -- Need for Mapping. The noise
subsection, 5-4 (D), of the Construction Impacts section, does not present a
comprehensible picture of the noise impacts to be received by properties adjacent
and near to truck routes, nor does it present a comprehensible picture of the
present and projected land uses along the haul routes. The fSEIS should present
clear, detailed, and understandable maps, with 60 and 65 LDN noise contours --
existing and projected -- for each haul route. The present discussion does not permit
policy-makers or citizens to reach any intelligent decisions on possible measures to
mitigate noise by route selection or alteration, by restraints on hours of use, or
otherwise, for one cannot tell what noise will be received by whom, when or where.
1-11. Other Construction Impacts -- Need for Mapping. Other construction
impacts, such as general traffic congestion, dust (see subsection (E)), ground
vibration, and restricted access to and from private property, should also be
displayed in map format in the fSEIS. It would be best if the same base maps were
used for all presentations of impacts, to facilitate comparability and assessment of
cumulative impacts.
1-12. Combined Construction Impacts -- Better Identification of Impacted
Areas. The mapping suggested in the two immediately preceding comments would
perhaps serve as a useful way in which to identify more clearly those locations that
might experience excessive detrimental impacts. The present text discussion at
subsection (F) would be much more useful with accurate mapping, and with text
discussion that could develop from study of such maps.
1-13. Construction Noise Impact -- Truck Noise Combined with Aircraft
Noise. Is it accurate to assume, as does the first bullet point, p. 5-4-14, that there is
no impact from truck noise if there is pre-existent aircraft noise? Isn't noise
cumulative?
1-14. Construction Noise Impact -- Night-time noise & traffic.
(a) Apparently it is planned to run the fill-hauling vehicles well into the evening
hours, and again early in the morning. We suggest that this will not do; further
thought needs to be given to restricting the hours for major hauling work that
would impact residential & health-care properties.
(b) The fSEIS should present clear schedules, including proposed daily hours
of operation, for the fill-hauling activity on the various routes under consideration,
to permit all concerned to understand the full impacts of this massive activity.
1-15. Construction Noise Impact -- Air Quality. The proposed, soon-to-be-
adopted US EPA standard for airborne particulate matter between 2 and 10 microns
in diameter should be addressed in subsection 5-4 (7).
1-16. Construction Impacts -- Lack of Quantification in Discussion of
Social Impacts. All of the discussion in subsection 5-4 (F) should quantified.
1-17. Construction Impacts -- Mitigation measures inadequate. As to
subsection (J), p. 5-4-19, we suggest that acquisition of some properties will not
mitigate impacts on other properties, and a complete mitigation program needs to
be developed in cooperation with the relevant municipalities, neighborhood & local-
business groups, schools, and residents and other occupants.
PART 2: AIR QUALITY
2-1. Air Quality -- Health Consequences. The dSEIS is silent as to air and water
pollution by particulate matter emitted from aircraft operations related to Sea-Tac.
(a) How much, and what types of, particulate matter is expected to be emitted
as the result of aircraft operations related to Sea-Tac, at each measuring date
(including year 2020)?
(b) What literature has been reviewed in this regard? Cite it.
(c) What are the anticipated health consequences from such pollution?
(d) The dSEIS is silent as to the proposed change by the US EPA of its
standards for particulate matter, which, as the preparers of the dSEIS surely
know, will bring particulate matter in the size range of 2.5 microns within EPA's
standards. What will the consequences be for Sea-Tac airport and its environs
when the new PM standard comes into effect?
(e) The dSEIS is silent as to the proposed change by the USEPA of its
standards for ozone, which, as the preparers of the dSEIS surely know, will
tighten the ozone standards considerably. What will the consequences be for
Sea-Tac and its environs when the new ozone standard comes into effect?
2-2. Air Quality -- Health Consequences. We note that there is not a word in the Air
Quality section of the dSEIS about the health consequences of the air pollution to be
anticipated from Sea-Tac operations in the future.
(a) What are the anticipated health consequences from Sea-Tac pollution
(including exhaust from aircraft using the facility)?
b) What literature has been reviewed in this regard? Cite it.
(c) What are the (alternative) mitigation measures proposed?
(d) What is the level of increased Cancer Risk to the population associated
with the Alternatives discussed in the SEIS. Provide the study which was done to
assess the increased level of cancer risks due to chemical and air pollution
impacts from Sea-Tac airport.
2-3. Air Quality -- Health consequences. We note that there is no discussion in the
Air Quality section of the SEIS of the health consequences of aerial fuel dumping
associated with Sea-Tac operations. It is well known that such dumping is a common
phenomenon, especially over Beacon Hill and Rainier Valley in Seattle. The SEIS admits
fuel dumping events occur from aircraft operating at Sea-Tac. The March 1, 1997 edition
of the Highline News reports that the FAA recorded an incident of fuel dumping which
occurred on July 8, 1996.
(a) Do the preparers disagree with the foregoing statements, & if so, in what
particulars & on what factual basis (citing available documentation)?
(b) What is the projected amount of future fuel dumping associated with Sea-
Tac operations?
(c) What are the anticipated health consequences from future fuel dumping
associated with Sea-Tac operations?
(d) What literature has been reviewed in this regard?
(e) What (alternative) mitigation measures are proposed?
2-4. Air Quality -- Will Aircraft Emissions Increase throughout the Planning
Period? It appears from the last sentence of sec. 5-2 1 (p.5-2-2), and from Exhibit 5-2-3,
p. 5-2-4, that the preparers of the dSEIS expect aircraft emissions of carbon monoxide,
ozone, and hydrocarbons to increase every year to the year 2010, even though emissions
of these substances from all sources in the so-called Region will decrease. Is this a correct
understanding? If not, what is being forecast in this regard?
2-5. Air Quality -- Chief Executive’s certificate. See sec. 5-2 7, p. 5-2-12.
(a) Does the statute (49 USC 47106(c)(1)(B) provide, as this section implies,
that the chief executive officer of a State may delegate his or her authority to
make the statutory certificate? If so, cite and quote the exact language.
(b) Did the letter of 20 December 1996 referred to p. 5-2-12 state that the
director of the Department of Ecology was acting for the Governor
(Washington's chief executive officer), under the provisions of the above-cited
Federal statute. Quote the exact language.
(c) What state-law authority permits the Governor to delegate authority under
the cited Federal statute? Cite and quote.
2-6. Air Quality -- Projections. Other commenters have advised us that the figures
for NOx emissions in the DEIS, FEIS, and dSEIS seem to bear no clear relationship to the
numbers of operations projected, the known emission characteristics of the fleet mix, or
other relevant factors. It seems that despite ever-increasing levels of operations in fact and
projected in the future, NOx emissions do not rise proportionately. Comment and explain.
Kindly set out the various NOx predictions put forward at various stages of this
environmental-review process (preferably in tabular or graphic form), and explain the
assumptions underlying the various projects.
2-7. Air Quality -- Particulate Emissions. Are particulate emissions from Sea-Tac
aircraft operations considered in the discussion of air-quality issues associated with third-
runway construction, or, have those emissions been removed from the relevant models?
2-8. Air Quality - Conformity provisions. We do not believe that the project
will be in compliance with the general conformity provisions of the Clean Air Act for
the following four reasons:
1. The project de minimus levels would be violated if proper input had been used in
the modeling of impacts.
2. The SEIS indicates several locations where pollutant concentrations will exceed
the National Ambient Air Quality Standards for NO2, CO and PM10.
3. The intent of the SIP is to reduce emissions and achieve attainment and
maintenance of the standards. This project increases emissions of CO and ozone
precursors without any control measures to reduce airport related emissions which
could jeopardize the maintenance status of the area. The potential for a new
violation of the PM10 standard from construction activities and exceedances of the
new ozone and PM2.5 standard would also violate the Clean Air Act and general
conformity regulations.
4. All predicted exceedances of the federal standards are within areas of public
access and represent ambient locations and therefore, must be mitigated.
The fSEIS should discuss compliance with conformity regulations and mitigation.
PART 3: NOISE
3-1. Is the Port Serious About Noise and Noise Mitigation?
(a) On page 5-3-2 the dSEIS states: "On the basis of scientific surveys and
analysis, the FAA has established 65 DNL as the critical level for the
determination of noise impacts." Authorities cited in support of this claim are
"Federal Aviation Administration Part 150 and the Federal Interagency
Committee on Noise" (FICON). The FICON document referred to fails to
establish or cite authorities establishing 65 DNL as the threshold for health
effects caused due to noise.(p.2-4). 14 CFR part 150 contains no provisions
establishing noise levels of 65 DNL as a threshold for determining health effects
caused due to noise. The Noise Expert Panel's Final Decision similarly
challenges the dSEIS's bald assertion that 65 dB DNL is the threshold for
determining impacts on populations exposed to noise. In their Final Decision on
Noise Issues" issued March 27, 1996 the Panel wrote: "The Port cites the 1992
FICON Report . . . since that FICON Report was issued, a considerable body of
medical literature has been developed, documenting the adverse effects of
exposure to noise levels in the 65 to 75 dB range, including psychological
distress, loss of concentration and reading comprehension, and other
physiological effects." (p.20) The fSEIS should cite the "scientific surveys and
analysis" which the dSEIS purports establish 65 dB DNL as the critical level for
determination of populations affected by noise?
(b) In our DEIS comments (COMMENT IV-1-7) we asked for a comprehensive
search of the scientific literature which cited all references, documentation, and
the scientific basis explaining the DNL 65 establishes the threshold of impacts.
No response was provided. We repeat our earlier comment and request a
response in the fSEIS. As we noted in our earlier comments, in a recent
rulemaking, the FAA apparently endorsed the EPA's position that it should
"modify the definition of (the noise study area) so as to eliminate the perception
that the area within the DNL 65 dB contour is the sole area to be considered for
noise impacts, while retaining the flexibility of extending beyond the DNL 65 dB
contour."
(c) Additionally, we provided in our earlier comments on the Draft EIS a copy of
the results of a search of scientific, medical and technical literature on the health
effects of airport noise. The results of this literature search turned up over 400
separate citations of publications of potential interest to investigators studying
this issue. Since our search additional information has come to light. We request
that the fSEIS review our previous DEIS comments as well as recent literature
concerning aircraft noise and request that it cite all references, documentation,
and the scientific basis explaining its assertion that DNL 65 establishes the
threshold of aircraft noise impacts.
(d) How much of its own money does the Port of Seattle (POS) plan to spend
for noise mitigation? It seems from p.1-14 that the insulation programs are
restricted to activates financed by FAA per Part 150 studies. Please do not
include funds received from other governmental bodies in the response.
(e) For what noise-mitigation activities will the Port of Seattle's (POS) own
money be spent (if any of the Port's money will be so spent)?
(f) What is the timetable for implementation of the noise insulation program.
Include a table showing the amounts in dollars which will be allocated year by
year for noise remedy programs through the year 2020.
(g) Include a copy of the interlocal agreements signed by local cities, including
Burien, Des Moines, Federal Way, Tukwila, Normandy Park, and SeaTac and
local school districts, including the Highline School District, which contain funding
commitments for noise programs, which will be executed prior to authorization of
the 3rd runway.
3-2. More Maps Needed. SEL contour maps should be prepared & included in
the fSEIS, comparable to the 65 DNL maps (Exhibits 5-3-1 & seq.) depicting the
100 dB, 90 dB, and 80 dB SEL noise contours for existing conditions as well as all
proposed options
3-3. Estimated Population Impacted by Noise.
(a) The assertion in 5-6 1 (B), and in the associated tables (Tables 5-6-1
through 5-6-3), that with increased airside activity under the preferred alternative
(100,000 operations per annum, is it not?) there will only be another 1280
people adversely affected (i.e., within 65 LDN contours). This assertion is not
supported by factual studies or comprehensible explanations. Please provide
both.
(b) If activity increases of 20 or 25 percent don't budge the 65 LDN contour by
more than a minor fluctuation (probably within the margin of observational error),
the logical conclusion is that the LDN metric is structured and computed in such
a way as to suppress recognition of actual noise impacts. If that is a wrong
explanation, provide the correct one, if there is one.
3-4. Latest INM Noise-Modeling Program Should Have Been Used. The DNL
noise contours were developed on the basis of the FAA's INM Version 4.11 noise
modeling program. This version of the INM does not represent the best available
methodology for modeling noise impacts. Version 5.0 of the INM program has been
available for years. Version 5.1 of the INM was released prior to the announcement
that a dSEIS would be issued. We find it appalling that the noise analysis for a
proposed project whose cost and impacts amount to over $7 billion dollars, is being
assessed by a consultant paid nearly $5 million dollars, apparenlty too cheap to
purchase the latest revision of the INM noise modeling program, costing some $250
dollars. Because the following comments reveal that the noise analysis in the dSEIS
is fatally contaminated with faulty assumptions and will need to be redone, the
revised analysis in the fSEIS should utilize the current version of the INM. We note
that the latest version of the INM (5.1) is capable of directly using INM version 4.11
files, and files from earlier INM versions can be used with minor changes.
3-5. Modeling Assumptions Should Have Been Stated.
(a) The dSEIS failed to include the modeling assumptions used in producing
the noise contour maps in the noise analysis. The Port/FAA have been
previously criticized for failing to produce the data assumptions used to produce
noise exposure maps. In their "Final Decision on Noise Issues" issued March 27,
1996 the PSRC Expert Panel wrote: "despite the Panel's specific request, the
Port failed to supply detailed information on the assumptions and adjustments it
used when it applied the INM to compute changes in (i) DNL contours and (ii)
the population adversely affected by noise . . . ". [p.15] The following data
assumptions used in generating the INM noise contours and analysis are
examples of what should have been included in the dSEIS and should be
provided in the fSEIS:
1. The definition of the approach and departure flight tracks.
2. Verification of the selected flight tracks with actual operation conditions,
correlation with radar data, etc.
3. Assignment of flight track segments
4. Identification of Aircraft types
5. Maximum gross takeoff weight
6. Maximum gross landing weight
7. Static thrust, and operational thrust levels
8. Noise curve selected for specific aircraft types
9. Flight profile of each aircraft modeled
10. Identification FAA approval for non-standard (including NDAP) INM
profiles use in model
11. Annual number of operations of each particular type of aircraft.
12. The type of engine associated with each type of aircraft modeled.
13. Data assumptions used for modeling taxiway noise
14. Data assumptions used for modeling run-up noise
15. Source data used to estimate affected populations
16. Source data for base map including topographical data
(b) We note that the absence of the modeling assumptions makes it
impossible for the reader to analyze the reliability of the resultant noise analysis.
We noted this in our scoping comments, and repeated this requirement later in
our comments on the draft EIS, that inclusion of the data assumptions
associated with analyses contained in the EIS documents was a mandatory
requirement to enable the public to make informed comments. This information
was not provided in the final EIS and again has not been included in this
document. Please provide it in the FSEIS.
(c) Our ability to make informed comments on the noise analysis in the dSEIS
has been further impaired by our inability to obtain the information from the
author of the SEIS through request made under Washington State's Open
Public Records Act. Attached as an Exhibit to these Comments is a copy of a
letter dated 7 March 1997 from Port of Seattle Planning Program Manager
Diane Summerhays, stating the information which provides the basis for the
modeling assumptions in the dSEIS NEMs is not available from the Port of
Seattle, a preposterous assumption since the SEIS is a joint Port of Seattle/FAA
publication.
3-6. NEM for 1996 Should Be Included. A noise exposure map (NEM) for the
year 1996 rather than 1994 should have been included in the fSEIS to allow a
comparison between most recent noise exposure conditions as compared to the
noise exposure predictions made for the years 2000, 2005, and 2010, &c.; The total
number of aviation operations in 1996 (395,000) exceeded the year 1994 operations
(345,052) by 44,957 operations. We note that the 1996 noise exposure map
produced during the recent Part 150 Update assumed predicted rather than actual
number of flight operations, &c;, for 1996 and therefore would not suit as a reliable
reference. A noise contour map showing actual noise exposure conditions at Sea-
Tac for 1996 is required to made a reliable comparison. Please provide it in
response to this comment.
3-7. NEM's Depicting Seasonal Variations of Air Traffic Should Have Been
Provided in the dSEIS The INM User's Guide states "It may be useful or necessary
to perform supplemental analysis for different times of the year or other time periods. For
Example, a supplemental analysis may be necessary for the spring season as compared
with fall and winter, if significant changes in fleet mix, flight operations, or flight tracks
are anticipated." (INM Version 5.1 User's Guide, p.2-2) Sea-Tac airport experiences
significant shifts in flight operations and flight tracks through the year. The 1991 Part
150 Update reported that in 1990, Sea-Tac airport was in South flow conditions 69%
of the year and in North flow conditions 31% of the year. (p.24) During the Months of
January through June and October through December SeaTac airport was in South
flow conditions 76% of the time. During the months of October and November Sea-
Tac was in South flow over 92% of the time. NEM's depicting seasonal noise
exposure should have been developed in the dSEIS and should be included in the
fSEIS. Please provide them in response to this comment.
3-8. 65 dB Noise Level Mischaracterized. On p. C-3-8, the dSEIS states that
65 dB is a relatively low environmental noise level". In their "Final Decision on Noise
Issues" issued March 27,1996 the Noise Expert Panel found "a considerable body of
medical literature has been developed, documenting the adverse effects of
exposure to noise levels in the 65 to 75 dB range, including psychological distress,
loss of concentration and reading comprehension, and other physiological effects."
Panel Order, p. 20. Cite the authority for the assertion in the dSEIS or remove it
from the final SEIS.
3-9. Correlation of Noise Exposure Map Contours with Port Remote Noise
Monitoring System Data. The Port of Seattle maintains 11 separate remote noise
monitoring system (RMS) stations in areas surrounding Sea-Tac airport. These
stations measure DNL (Day-Night average noise level) as well as time above (TA)
noise metrics, single event level (SEL) as well as other metrics. Remote NMS data
recorded for the year 1996 should have been presented in the dSEIS and correlated
to the 1996 NEM for the base year study. The compared noise levels should include
the DNL, and time above (TA) as well as the single event level (SEL) metrics
recorded at each of the eleven (11) RMS stations. A table should be included
comparing the respective DNL, TA and SEL metrics from the RMS system with the
level predicted in the INM model.
An error analysis showing the statistical correlation between the predicted INM
contours and the noise measurements recorded through the Port's Remote RMS
should also have been included in fSEIS noise analysis. Provide this comparison
and analysis in the fSEIS.
3-10. The INM Predictions of SEL are Invalid. The INM was not designed for
single-noise event prediction., but rather for estimating long-term average input
data. The FAA's INM User's guide states that comparisons between measured data
and INM calculations must be considered when modeling SEL noise levels with the
INM. (Integrated Noise Model (INM) Version 5.1 User's Guide, p.2-3) The dSEIS
contains no comparison between actual actually measured SEL noise levels and
SEL noise levels predicted using the INM noise modeling program for the base year.
The fSEIS should provide this and an alternate methodology for predicting single
event noise impacts for future years and include contour maps depicting future year
SEL noise conditions.
3-11. Questionable INM Input Assumptions Concerning Utilization of
Runway
fSEIS
(a) The flight track for jet departures in Table C-3-16 indicates that the utilization
of runway 16X for departures of heavy aircraft (exceeding 300,000 lbs.) under
north flow conditions is estimated to be 1% for each of three (3) departure flights
tracks (HT11, HT17, and HT33) and that the noise impacts of the third runway
are based on the assumption that it would be utilized by operating departing
flights along only one flight track which would constitute only 13% of the airports
operations. Please reconcile the proposed utilization of these runways with the
cost-benefit analysis which should also be provided in the fSEIS. Indicate in the
comments the section number where the cost-benefit analysis assuming this
runway utilization can be found.
(b) Under south flow conditions the dSEIS assumes use for runway 16X (third
runway under north flow conditions) is 1% for each of three new flight tracks
under both day-time and night-time operations. The utilization of the third runway
under south flow conditions is 13% for one individual flight track under south flow
conditions. Please reconcile the proposed utilization of these runways with the
cost-benefit analysis which should also be provided in the fSEIS. Indicate in the
comment the section number. where the cost-benefit analysis assuming this
runway utilization can be found.
(c) The allocation of usage of the third runway under south flow conditions shows
one flight track (TOl) accommodating 2% of the operations of the 3rd runway of
heavy aircraft (exceeding 300,000 lbs.) along only one flight track whose
operations would 3% of the airports operations. Table C-3-16 makes similar
presumptions for other aircraft types. Evaluation of noise impacts for jet aircraft
weights less than 300,000 lbs. are based upon the assumption that the third
runway would be utilized by aircraft operating with use of three separate flight
tracks (JTll, JT15, and JT 33), each of which would utilize only 1% of Sea-Tac
Airport's flight operations. Under south flow conditions the dSEIS bases its noise
prediction on the assumption the third runway would be utilized by jet aircraft
(weighing less than 300,000 lbs.) operating with use of one flight track, whose
operations would constitute only 2% of Sea-Tac Airport's operations. The noise
analysis for the new runway for the year 2010 also estimates that the noise
impacts based on the assumption that the third runway would be used by
propeller aircraft less than 1% of the time along three flight tracks under north
flow conditions (PT11, PT13, and PT 15), while the noise assessment is based
on projections that aircraft operations of approximately 2% of Sea-Tac’s
operations would occur under south flow conditions. Please reconcile the
proposed utilization of these runways with the cost-benefit analysis provided in
the fSEIS. Indicate in the FEIS comments the section where the cost-benefit
analysis assuming this runway utilization can be found.
3-12 Prefatory note on sections 3-13 - 3-25. Specific concerns about the
assumptions being made in the INM which have not yet been reported for public
review and comment, and are requested to be provided in the fSEIS are as follows:
3-13. Estimates of Affected Population. During the Puget Sound Regional
Council's Expert Panel Hearings last year Dr. Sanford Fidell noted that "adjustments
on the order of 2 dB made by the Port to reconcile differences between measured
and predicted SEL values "could easily lead to errors as great as thousands of
people in estimates of populations exposed to similar noise levels in different time
periods." (Testimony Presented by Dr. Sanford Fidell to the Expert Arbitration Panel
on Noise and Demand/System Management on Phase II Noise Issues, p.2).
(a) Provide documentation from U.S. Census Bureau records including the
census tract information used to estimate the total population affected by noise
levels of 55 dB, 60 dB, 65 dB, 70 dB, and 75 dB DNL.
(b) Provide a description of the analysis used to predict the impacted
population in various noise exposure zones (55-60 dB, 60-65 dB, 65-70 dB, 70-
75 dB, 75+ dB, &c.;) in the fSEIS. Include the analysis used to determine the
margin of error of the estimation of the impacted populations with confidence
intervals and sensitivity tests to support the statistical reliability of the dSEIS
data.
3-14. Ground Noise. Previous Sea-Tac noise exposure maps (NEMs) have not
included the impacts of ground noise from Sea-Tac airport. Recent versions of the
INM (Versions 3.9 and later) are capable of integrating runup noise and taxiway
noise into the NEMs. Aircraft runup noise and taxiway noise parameters were not
included in the input files used to generate the Year 1990 and 1996 noise exposure
maps (NEMs) produced in Sea-Tac's last (1991) Part 150 Update. The 1991 study
did find that DNL noise levels at remote monitoring stations RMS 5 (S.171st & 10th
Avenue S.) and RMS 10 (S.192nd & 11th Avenue S.) located immediately West of
Sea-Tac read higher than predicted by the 1990 NEM by 3.1 and 1.7 decibels,
respectively. A professional engineer conducted an independent study which
measured Sea-Tac's 65 dB DNL noise contour as far as 4,000 feet west of the
location shown on the Port's 1990 NEM.(Sea-Tac Noise Study prepared for RCAA
by Errol Nelson PE, January 1993 previous submitted by the RCAA). The SEIS
should publish the data assumptions used to model runup noise and taxiway noise
in the INM noise exposure maps published in the fSEIS.
3-15. Assumptions about Future Noise Levels Erroneous. Section 6 (p. 5-
3-7) makes two absurd assumptions. First, that "Future impacts will be less than
the current noise exposure regardless of which Master Plan Update alternative is
pursued", and second, "The 'With Project' alternatives would result in slightly
greater noise exposure in comparison to the Do-nothing Alternative. Justify these
assumptions or correct them.
3-16. Noise Barriers. Strategies to reduce noise impacts on surrounding
communities utilizing noise barriers should be considered in the fSEIS. We note the
FAA recently approved plans for the construction of a noise berm on the western
edge of airport property in Paine Field’s Part 150 Master Plan and Noise Study
Update issued October 1996. The noise berm is being provided to "protect
residences just west of Paine Field Boulevard from experiencing higher aircraft
noise than they presently experience. Similarly, the construction of a noise berm on
the West side of Sea-Tac Airport would shield residents in the West area of the City
of SeaTac, and residents of Burien and Normandy Park from harmful and annoying
noise caused by runups, takeoffs, and landings. Indicate what written financial
commitments the Port of Seattle has made in conjunction with the construction of
noise berms for attenuation of aircraft noise from Sea-Tac airport. Include
documentation evidencing the Port's financial commitment in the final SEIS. Provide
maps showing proposed berms. Provide drawings showing typical berm
construction, as planned.
3.17. Levels of Annual Operations Used in Future-Year NEMS. Total number of
operations projected for future-year periods are problematic in the dSEIS. Currently,
there exist at least a dozen projections of air traffic activity at Sea-Tac for the year
2000. Forecasts of the total number of Sea-Tac airport air carrier operations in the
year 2000 have ranged from 260,810 operations per year to 452,800 operations per
year, a variation of 191,990 operation per year. The latest Terminal Area Forecast
for Sea-Tac airport developed by the Federal Aviation Administration should be
utilized in developing the future-year noise exposure maps in the SEIS.
3-18. Verify Aircraft Flight Profiles Used in the INM. A 1981 FAA study ("A
Comparison of FAA Integrated Noise Model Flight Profiles with Profiles Observed at
Seattle-Tacoma Airport", George W. Flathers, December 1981, Report No. FAA-
EE82-10) determined that aircraft flight profiles at Sea-Tac were not consistent with
the profiles used in the current version of the INM noise modeling program. This
study noted that the departure profiles used in the INM "were constructed under the
assumption that, for all aircraft types, airlines employed the FAA noise abatement
departure profile as outlined in AC 91-53. However, the observed data for the low-
bypass-ratio engined aircraft in the study (DC-9, B-737, B-727) suggested that for
these three types of aircraft, this may not be the case."
The 1991 Part 150 study assumed that Stage 2 aircraft followed the FAA's
suggested Noise Abatement Departure Profile (AC 91-53) which calls for thrust
reduction after takeoff upon reaching 1000 feet elevation. (Noise Exposure Map
Update: 1991 prepared by the Port of Seattle April 1992, p.54) However, no
substantiation that these procedures were being followed by the airlines serving
Sea-Tac was provided in the update.
We further note that the FAA now requires approval of Noise Abatement
Departure Profiles (NADP) in the INM model. The INM User's Guide specifically
states: "INM 5.1 does not contain pre-approved NADP's . . .". (p.2-2) No
documentation was provided in the dSEIS indicating the FAA has approved NADP
flight profiles for use in the INM.
Evidence including tower orders, adoption of standard or NADP operations for
departures by the scheduled air carriers, radar data, etc. should be provided to
corroborate that operational assumptions used to predict noise exposure in the
NEMs are actually being followed by aircraft at Sea-Tac. The fSEIS should contain
this documentation. Additionally, publish NEM's which show alternative noise
contours assuming (1) the use of NADP in the INM model and (2) assuming
standard departure procedures. Publish documentation provided by FAA approving
the use of NADP flight profiles in the NEMs.
3-19. Verify Fleet Mix Assumptions. Careful consideration must also be given to
the parameters used in the INM noise model used to estimate fleet mix. The 1996
NEM produced in the recent Sea-Tac Airport Part 150 update assumed Stage 2
aircraft operations constituted 14.73% of Sea-Tac's total flight operations. According
to the Port of Seattle's Noise Abatement office the percentage of Stage 2 jet
operations during 1996 exceeded this level. The fSEIS should provide the
assumptions underlying its predictions of future aircraft fleet mixes.
3-20. Verify Aircraft / Engine Types Used in the INM. Careful verification of
aircraft types and engine models selected for use in the model should be made by
the consultant. The INM noise modeling program allows the user to select a noise
curve for each type used in the INM to match a specific aircraft/engine configuration.
Noise levels produced by the same type of aircraft vary considerably depending on
engine type. For example, a model 737-300 equipped with JT8D-15QN engine is
5.6 dB louder on takeoff than the same model aircraft equipped with JT8D-7QN
engines (Estimated Airplane Noise Levels in A-Weighted Decibels, AC No. 36-3F
published by FAA, August 10, 1990, p.23).
Noise levels on departure vary by as much as 10.2 dB comparing a Stage 2
727 outfitted with JT8D-17RQN engines compared to a 727 equipped with model
JT8D9FCD engines. Accumulation and propagation of error through the INM noise
model should be limited by verification of aircraft type and engine parameters. The
fSEIS should provide .documentation that verifies that the engine configuration
assumed comports with the specific aircraft type designating in the INM used in
generating noise exposure maps for Sea-Tac.
3.21. Verify Statistical Reliability of INM Data. During their recent (1996)
investigation into the Port of Seattle's Noise Exposure Maps (NEMS) the Expert
Arbitration Panel requested that the Port (i) present information on confidence
intervals to support the statistical reliability of its data, (ii) provide documentation of
the assumptions and adjustments it made when developing the INM contours, (iii)
show the assumptions used for estimating impacted populations, and (iv) produce
sensitivity tests to evaluate the effects of these assumptions. The Port did not
comply with these requests (p.14). The above information is similarly missing in the
analysis in the dSEIS. Provide this analysis in the fSEIS.
3.22. Include Noise Contributions from Other Area Airports in NEM's. The
Noise Exposure Maps should integrate the noise level contribution from other area
airports, particularly Boeing Field, located approximately six (6) miles north of Sea-
Tac. The DNL values of noise generated from Sea-Tac should be added to the DNL
noise levels produced from Boeing Field to produce and accurate and realistic
assessment of the combined noise impacts of these two airports upon the citizens in
the south Seattle, south King County areas. (See p. 6-3 of INM User's Guide.)
3.23. Base Map. Version 5.1 of the INM is capable of generating noise contours on
U.S Coast and Geodetic Survey (U.S.G.S.) maps which model the topographical
feature of land surrounding the airport facility being modeled. The fSEIS should
present NEMs that incorporate the topographical features of U.S.G.S. maps into the
noise model and calculate DNL, TA, and other metrics each of the locations
modeled.
3-24. Noise Abatement Departure Profile. The Noise Expert Panel also
recommended that the Port/FAA evaluate the utilization of noise abatement
departure corridors to minimize aircraft noise impacts and "Evaluate, with FAA and
community input, the potential net benefits of a noise abatement departure profile
employing a steeper angle of climb, coupled with an expanded residential acquisition
and insulation program if, as a result of a steeper departure profile, the 75 dB DNL
contour expands in the immediate vicinity of the airport while areas farther out receive
benefits."
Provide an analysis of the effects on noise exposure of the population in the 60 dB
DNL and above noise affected population through adoption of noise abatement
departure profile employing a steeper angle of climb. Include revised noise contour
maps for the future year 2000, 2010, and 2020 showing the locations of the 60 dB,
65 dB, 70 dB, and 75 dB DNL as well as the 70 dB, 80 dB, and 90 dB SEL noise
contours surrounding Sea-Tac airport based upon the level of operations projected
in the SEIS using the noise abatement departure profiles recommended by the
Noise Expert Panel.
3-25. Preferential Runway for Noise Abatement. The Noise Expert Panel also
recommended that the Port/FAA evaluate the utilization of a preferential runway
during periods of low activity:
e. Evaluate, with FAA and community input, the potential net benefits of
preferential runway use during "low activity" periods (would more use of the east
runway, for example, result in reduced overall population noise exposure?) --
coupled with an expanded residential insulation and acquisition program, as
needed.
Include in the SEIS an analysis of the potential changes in noise impacts which
would result through the preferential use of runways during low activity period to
achieve a reduction in noise impacts.
3.26. Part 161. Recent policy shifts by the FAA have indicated increased
flexibility by the FAA in implementing enhanced noise reduction programs at airports
adopting enhanced noise restrictions under Part 161 regulations. Recently in
connection with its approval of a Part 150 Noise Compatibility Program for Pease
International Airport in New Hampshire, the FAA approved funding for a Part 161
study as an element of the airport's Part 150 program (Airport Noise Report, April
15, 1996). Citizens and local municipalities surrounding Sea-Tac airport have
suggested that the Port of Seattle engage in a Part 161 study in conjunction with a
Part 150 Update Study currently underway at Sea-Tac. (See also ACC testimony
before Noise Expert Panel dated Feb. 16, 1996.) In November 1995 the King
County Council adopted Resolution No. 9709 which funded a Part 161 program to
establish current and future noise restrictions at Boeing Field. The final SEIS should
comment on the impact future Part 150 and Part 161 programs will have upon
future development at Sea-Tac Airport.
3-27. Social Surveys. In its Final Decision on Noise Issues issued March 26,
1996 the Expert Panel recommended that social surveys be utilized to evaluate
community attitudes concerning the impacts of airport noise upon citizens. The
Panel recommended "That the Port and the organizations representing the affected
communities jointly sponsor social surveys at regular intervals to assess the
effectiveness of future noise abatement and mitigation measures in terms of perceived
noise impacts.
We concur with the view expressed by the Port's noise consultants in the 1993
AIRTRAC Final Report (p. 3-33): 'The way to avoid incorrect predictions of community
response to a ... [noise reduction] action is to ask the community directly how it feels
about a particular airport action and the proposed mitigation program connected to it."
Explain why the Port/FAA have not conducted the social surveys recommended by
the Expert Panel as part of its review of environmental and social impacts.
3-28. School Sound Insulation. The Expert Panel recommended:
"That, with respect to the Noise Remedy Program, the Port take the following
actions:
a. Begin a rapid, full-scale program of school insulation as soon as the
impasse with the Highline School District is resolved, with the maximum feasible
commitment of re-sources and the earliest possible completion schedule."
Include a copy of the written financial commitment the Port of Seattle has made in
conjunction with the insulation of schools in the Highline School District.
3-29. Public Buildings Sound Insulation. The Expert Panel recommended:
"That, with respect to the Noise Remedy Program, the Port take the following
actions:
b. Complete the "sensitive-use" public buildings insulation pilot studies and
fund the full program envisioned in the Noise Mediation Agreement, as well as a
program for insulation of multi-family dwellings, with an aggressive schedule to
allow completion as soon as possible. The Port Commission is on record as
committed to these programs."
Indicate what written financial commitments the Port of Seattle has made in
conjunction with the insulation of public buildings. Include in the fSEIS documentation
evidencing the Port's financial commitment.
3-30. Expand Residential Acquisition Program. It is significant to point out
that the boundaries of the Port of Seattle's present noise remedy program still
remain based upon the Port of Seattle's earlier 1982 estimate that only 260,810
operation per year would occur at Sea-Tac in the year 2000. The annual operations
at Sea-Tac currently outstrip the year 2000 operation prediction by approximately
136,000 operations per year. The Expert Panel noted that the expected reduction in
total population exposed to noise levels of 65 dB DNL and above has not occurred
as predicted. The Panel recommended:
"c. Evaluate the possibility of an expanded residential acquisition program
offering more of the most severely impacted people the buy-out option, even if
no additional Federal money is made available for this purpose. While relocation
is not desired by all (nor easy for anyone), the environs of a major airport are
plainly not the best location for residential neighborhoods."
The fSEIS should indicate what steps the Port plans for expansion of its residential
noise remedy program eligibility area to mitigate the impacts of residents. Indicate
what written financial commitments the Port of Seattle has made in conjunction with
the expansion of the Port of Seattle's noise insulation program. Include
documentation evidencing the Port's financial commitment in the final SEIS.
3-31. The fSEIS appears to assume the majority of housing construction in this
region is cold weather construction. It is not. Homes here, for example, do not have
the insulation, storm and or thermal windows and other cold weather construction
techniques found in other cold-weather areas of the country or the air conditioning
found in warm climates. The SEIS should reflect the temperate climate construction
used in this area.
3-32 Cold-weather construction: only 10%? In some places in the dSEIS the
drafters appear to assume that cold weather construction is either brick or masonry
construction. At others, it states that 10% of the housing is masonry or brick.
(1) If it is only 10%, not the majority of the housing, the figures should be
reworked and it is not clear in the dSEIS if they were.
(2) The fSEIS should distinguish masonry from brick, as the dSEIS fails to
do-what percentage of each. There are very few stone masonry houses in this
region of the country. Furthermore, the dSEIS does not distinguish brick construction
from brick veneer, which is essentially wood construction and should be so treated.
The SEIS should correct this error.
PART 4: WETLANDS & WATER QUALITY IMPACTS
4-1. Miller Creek Relocation.
(a) How does the Port propose to effect a plan to relocate and re-channelize
Miller Creek, as well as to increase the rate of flow in Miller Creek, given that it is
under an existing court order (consented to by the Port, as well as King County),
forbidding it to undertake such actions? We previously provided copies of these
settlement agreements (Kludt et al. v. King County and the Port of Seattle, King
County Superior Court, Case No. 762259) which prohibits the re-channelization
of Miller Creek and the increase in flow in Miller Creek, to the authors of the
dSEIS. Nevertheless, this action is now apparently contemplated in the dSEIS.
A previous response to our DEIS concerns about proposed plans to alter Miller
Creek from the Port/FAA cited a completely unrelated matter before the State's
Pollution Control Hearings Board. We again invite the commenters to provide a
fSEIS which acknowledges the existence of the settlement agreements with the
Port and King County which exerts local pre-emption of planning activities in the
Miller Creek Basin. We look forward to comments responding to this matter in
the fSEIS. Does the Port/FAA acknowledge the previously mentioned settlement
agreements as pre-empting Port/FAA control over planning in the Miller Creek
Basin?
(b) Has the Port advised the U.S. Army Corps of Engineers of the court
ordered settlement agreement referred to in (a)?
4-2. JARPA & §404 Application.
(a) The texts of the applications, as well as the Miller Creek Relocation Plan,
Wetlands Relocation Plan, and accompanying drawings and other documents
referred to in Section 5-5 1, p. 5-5-1, should have been part of the dSEIS and
should be included in the fSEIS. Please provide them in response to this
comment.
(b) How as a practical matter do the proponents expect the general public to
comment on this subsection when the most important documents (the
applications) are available only in two remote locations? Non-availability of these
documents prohibits the review of impacts or the proposals made in the
application for the Corps of Engineers Wetlands permits and impairs the public’s
ability to make informed comments on the SEIS.
4-3. Use of out-of-basin wetlands replacements. We are aware that other
commenters have commented, and intend to further comment, on the
inappropriateness of substituting wetlands in one basin for those damaged in
another, which is proposed here. We join in such comments, and ask for a full
explanation of the legality (if any) and practicality of the proposal. The fSEIS should
specifically address, city by city, the local codes that require wetland mitigation to be
within the same drainage basin, as well as any other relevant legislation or
regulations.
4-4. Sea-Tac International Airport Storm Drainage Plan Ignored. While we
have been unable as of this writing to secure a copy of the document, we are well
aware that on behalf of the Port, the firm HDR Engineering, Inc., has issued a multi-
volume final draft report, dated February 1997, entitled "Sea-Tac International
Airport Storm Drainage System Comprehensive Plan".
(a) Do the preparers deny the existence of this report?
(b) Why was this report not referred to in the dSEIS?
(c) What is the relationship between the Plan set out in the referenced
document and the December 1996 Miller Creek Relocation Plan, prepared by
Parametrix, Inc., for Landrum & Brown, a consultant to the Port? Set out in
detail and in format permitting easy comparison the actions proposed, the
adverse impacts thereof, & the proposed mitigations of such actions, as
proposed in the two different documents & in the dSEIS.
4-5. Underlying Aquifers. Why is the dSEIS silent on the subject of impacts on
aquifers known to underlie Airport property? This subject should be covered in the
fSEIS.
4-6. Des Moines Creek.
(a) We do not find -- the lack of an index is a real handicap here -- any mention
of impacts on Des Moines Creek in Section 5-5 or elsewhere in the dSEIS. If
Des Moines Creek was mentioned, the response, we are confident, will point out
the location of such mention.
(b) On the conclusion that the dSEIS ignores Des Moines Creek, we ask that
the fSEIS explain why, in light of the fact that the Port has told the U.S. Army
Corps of Engineers in Attachment B to its Section 404 application dated 18
December 1996 that "[i]mpacts to Des Moines Creek will occur in later phases
of construction activity", these impacts were not discussed in subsection 5-5 1,
or anywhere else in section 5-5.
(c) What are the projected impacts to Des Moines Creek, when will they
happen, what are the consequences of the impacts, and what are the proposed
mitigation measures (including the costs thereof)?
(d) As mentioned above any mitigation plans should be sequenced such that the
mitigation is in place prior to the action for which the mitigation is required.
4-7. Impact on Fish Populations.
(a) While two goals are stated (p. 5-3-20, Goals 2, 5) in regard to enhancing
fish populations in one of the creeks to be impacted by the project, nothing is
said as to whether, or to what degree, either goal will be met. The fSEIS should
show how each of the goals, including fish-enhancement goals, will be met for
Miller Creek if relocation were to occur.
(b) The dSEIS is silent as to impact on fish populations in streams in the
affected area. The fSEIS should cover this topic.
4-8. Useful Life. The dSEIS says that the useful life of the runway will be
approximately 5 years. (The revised completion date for the 3rd runway is the yeas
2005. According to EXHIBIT 2-7 on page 2-25 of the dSEIS, Sea-Tac airport with a
3rd runway will reach its "[p]ractical capacity per NPIAS" in the year 2000. The
same chart in the SEIS shows that according to FAA terminal area forecasts
(TAF'S) Sea-Tac airport equipped with a 3rd runway would be classified as
"Severely Congested per NPIAS" by the year 2010. Please explain what the total
amount of costs of this project will be, including capital costs, mitigation costs, as
well as accrued financing and amortization costs. What is the cost per year of the
new runway's useful life? Provide an analysis which derives the rate of return on
investment for this project?
4.9 Lost Opportunity Costs. The fSEIS should discuss the lost opportunity costs
to the region of spending public money on the 3rd runway project as opposed to
spending it on alternatives.
PART 5: SOCIAL, SOCIO-ECONOMIC, & LAND-USE IMPACTS
5-1. Noise and Land Use. We comment again, in connection with Subsection
5-6 1, that the 65 LDN metric is no fair measure of adverse airport noise impacts on
land use. The Expert Arbitration Panel, the US EPA, the Natural Resources Defense
Council, and many commenters in this long process all have pointed out various
weaknesses of the LDN metric. We call, once again, for the use of more reasonable
metrics.
Single-event levels are studiously ignored in the discussion here commented on,
yet everyone knows -even government environmental specialists -- that, more than
anything else, it is the single noise event (be it from aircraft, motor vehicles, gunfire,
human voices) that disturbs people in their everyday lives. We challenge the SEIS
preparers to find anyone disturbed by a year-long average of aircraft noise. It may
be that the FAA is cheerfully content to remain the prisoner of its own
misconceptions on this matter, but the Port of Seattle, which is NOT bound to limit
its good deeds to the cramped style of FAA, should now rise to the occasion and
use more appropriate noise metrics. If there are any good reasons (a) to disregard
the criticisms of the 65 LDN metric or (b) to stick with that metric criticisms
notwithstanding, what are those reasons?
5-2. Noise and Land Use.
(a) The fSEIS should present noise contour maps on the basis of 55 LDN
contours as suggested by US EPA.
(b) Single-event levels should also be presented in a comparable mapping
format showing 100 dB, 90 dB, and 80 dB SEL noise contours.
(c) Tables showing 55 LDN & SEL measurements should be presented,
comparable to Tables 5-6-1 through 5-6-3.
(d) The numbers of single-family homes, duplex/triplex homes, apartment
houses, places of religious activity, schools, nursing homes, hospitals, &c.;,
should be reported in terms of the other metrics suggested in this and the
immediately prior comment. (c)
5-3. Social Impact Discussion Grossly Deficient. Subsection 5-7 2, Social
Impacts, is grossly deficient, to the point that some observers would think that it is a
deliberate insult to the adversely affected communities.
(a) The subsection correctly recognizes that social impacts include residential
and business displacement, disruption of existing communities, disruption of
planned development. P. 5-7-1. After setting out the number of single-family
properties, apartments, and businesses to be acquired, there is not a single
word about the consequences. Why not
(b) Is it the intention of the dSEIS preparers to refuse to discuss the subject of
residential displacement?
(c) Is it the intention of the dSEIS preparers to refuse to discuss the subject of
business displacement ?
(d) Is it the intention of the dSEIS preparers to refuse to discuss the subject of
disruption of existing communities?
(e) Is it the intention of the dSEIS preparers to refuse to discuss the subject of
disruption of planned development?
(f) Each of the matters referred to in comments 5-3 (a) - (e) should be
discussed in detail in the fSEIS.
5-4. Social Impacts: Pending Study Ignored; Depression of Property Values
Ignored.
(a) In addition to failure to discuss the very impacts that it recognizes, the
dSEIS subsection 5-7 2, Social Impacts, fails to take into account the State-
funded impact study now being conducted by the HOK study team, a draft of
which was released last Fall. Why was this study ignored? Why were no
responses to the issues raised reported in the dSEIS?
(b) Will the fSEIS take into account the final, published version of the HOK
study? If not, why not?
(c) The HOK study describes in detail a major adverse socioeconomic impact
that is not discussed in the subsection being discussed: depression of property
values. Did the preparers fail to discuss this subject because they believe that
there is no depression of property values resulting from airport-related noise? If
not, why was this subject not discussed in dSEIS?
(d) If the preparers agree that property-value depression is a real impact, do
the preparers have an estimate of the dollar amount of the property-value
depression resulting from Sea-Tac-related noise? What is that dollar amount
and how was it computed?
5-5. Induced Socio-economic Impacts: Pending Study Ignored; Loss of Tax
Revenues from Real-property Taxes.
(a) We regard the notion of separating "Social Impacts" from "Induced Socio-
Economic Impacts" as nonsensical, and request that in the fSEIS the discussion
of the two identical topics be combined.
(b) The dSEIS fails to take into account the above-mentioned draft HOK study,
which sets out, even in its preliminary, draft form, enormous losses of revenues
to municipalities in the vicinity of the Airport as the result of airport-related noise.
Why?
(c) The HOK study gives much higher numbers for these tax-losses than does
the dSEIS. The dSEIS provides no explanation of its tax revenue-loss figures,
whereas the draft HOK study sets outs its methodology & results in detail. How
did the preparers of the dSEIS arrive at their numbers?
(d) Explain & justify the differences between the dSEIS tax-loss numbers and
the tax-loss numbers in the HOK study.
(e) Provide comprehensive evaluations, based on valid, cited authorities, as to
any offsetting revenue gains that the preparers expect the affected
municipalities to receive as the result of expanded Airport activity.
(f) What mitigation is proposed with regard to lost real-property tax revenues?
Provide a copy of the real-property tax mitigation plan in the fSEIS.
(g) The fSEIS should comment in detail on the conclusions of the HOK team
that gains from Airport activity and losses therefrom do not fall proportionately
on the populations, individuals, or municipalities involved. Chapter 1 of the draft
study shows that the neighboring communities derive little of the benefits and
most of the negatives. This is a major conclusion, new information in this
environmental review process, and deserves the fullest examination in the
fSEIS, including much more extensive mitigation measures than have been
proposed to date.
5-6. Induced Socio-economic Impacts: Pending Study Ignored;
Demographic Changes.
(a) The dSEIS does not discuss impacts on community demographic profiles
from Sea-Tac expansion. The above-mentioned HOK study indicates significant
impacts from changes in demographic profiles. Why is the dSEIS silent on this
matter? The fSEIS needs to examine this problem in detail, & to recommend
relevant & sufficient mitigation measures.
(b) Changes in demographic make-up of affected communities are shown in
the draft HOK study to result in widespread changes in employment patterns.
These changes seemingly are not recognized in the dSEIS nor does the dSEIS
take into account in its optimistic view of the economic impact expansion on
nearby communities the depression of average income, the increase in socially-
dependent individuals and households, the loss of existing businesses, and the
consequent diminution of sales-tax & related revenues for the nearby
communities. This subject (i) needs to be addressed in the fSEIS, & (ii)
appropriate mitigation measures need to be suggested therein.
(c) Impacts from demographic changes are shown in the draft study, albeit not
in great detail, to have a damaging impact on the local public-school district.
This subject (i) needs to be addressed in the fSEIS, & (ii) appropriate mitigation
measures need to be suggested therein.
5-7. Inappropriate Shifting of Social Burdens. Massive Airport development
is shown in the HOK study to result in billions of dollars of social burdens. Careful
studies of such matters as origins of local residents using the Airport for travel
purposes, and location of persons employed at the Airport or in direct association
with Airport activities, such as those already done by the HOK team, strongly
indicate that the benefits of the Airport are enjoyed by persons and communities, for
the most part, well removed from the facility. The burdens, including loss of property
values, diminution of real property tax revenues, loss of businesses, destruction of
residential and business communities, increased social-welfare burdens, and the
like, are directed upon the neighboring communities. The Airport & its employees &
users gain; the local communities & their residents lose. Fundamental fairness
would seem to dictate that the Airport itself should be the vehicle by which society at
large accumulates, and redistributes, the funds & other assets needed to redress
this balance (in much the same way that insurance serves the social purpose of
evening out the unequal burden of risk-of-loss from societally approved
transportation facilities such as highways). The fSEIS needs to address, in a global
manner, how this unequal sharing of benefits and burdens is to be remedied.
5-8. Inappropriate Shifting of Social Burdens -- Executive Order 12898.
One effort to prevent inappropriate shifting of social burdens is Executive Order
12898, the Executive Order on Environmental Justice. The dSEIS is silent about how
the dSEIS addresses impacts associated with this order, its requirements, and the
disparate impacts of Sea-Tac activities that may fall within the reach of the order.
The proponents/preparers are well aware of concerns expressed in many different
ways about disparate impacts of Sea-Tac activities on populations specially
protected by the Order, and it would be burdensome to include here the many
letters, newspaper articles, and other documents reflecting those concerns & their
expression. Many have been previously submitted to the Port of Seattle, by local
residents, elected members of the King County Council, the city of Seattle, and local
representatives of the State Legislature.
We call particular attention to the state environmental policy act (SEPA)
administrative appeal of the FEIS approval filed by Ray Akers & the information
found therein concerning the impacts upon his neighborhood in the Rainier Valley
area which the dFEIS has chosen to ignore. The fSEIS is obliged by law to deal with
the E.O. 12898 issues in detail, with accuracy. We note with alarm that the residents
of South Seattle have not been informed of the impacts which their community
would be subjected to due to the Port/FAA's disregard of proper public notice and
advertisement of the dSEIS. (We have elaborated on the Port/FAA failure to provide
proper notice concerning this action in Part 8 of our comments.)
PART 6: ALTERNATIVES
6-1. Use of Other Modes of Transportation As an Alternative to Project.
See sec. III.1 (A) (p. 3-1). As was argued in RCAA Comment II-44 (h) to the DEIS,
when 'edge' conditions are reached in airport capacity, any measure that diverts air
traffic has a disproportionately beneficial, and cost-effective, impact. See also RCAA
Comment II-46, II-55(b)(1).
(a) The responses to the cited comments failed to address the 'edge' effect
arguments, which leads to the conclusion that they are unanswerable, since no
reason for ignoring them was offered.
(b) The proponents should take the opportunity of this SEIS process to
evaluate the beneficial impacts from the seemingly marginal improvements that
could be experienced when Sea-Tac surpasses the 380,000 to 400,000 annual
operations level, and begins to suffer markedly increased delay (cf. dSEIS
Exhibit 2-7, p. 2-26).
(c) The fSEIS should report more fully on the big change of heart as to future
rail development in this State experienced by the Department of Transportation
immediately after the Expert Arbitration Panel’s ruling on rail alternatives. It will
be recalled that the DOT told the Panel that faster rail was utterly impractical.
Then, after the Expert Panel's Dec. 8, 1996 Order was issued in reliance on the
Department of Transportation's utterly negative evaluation, WSDOT turned out a
big publicity blitz, seeking support for its program, seemingly developed
overnight, for short-term implementation of faster rail and issued its study.
Witness the Jan. 4, 1996 Seattle Times article reporting WSDOT's release of its
Options for Passenger Rail in the Pacific Northwest Rail Corridor study. The rail
alternative should be re-examined in light of the now-positive evaluations of the
Department and its previous reliance that a 3rd Sea-Tac runway would be
available to provide additional capacity by the year 2000. In its Final Order on
Phase II Demand/System Management Issues issued December 8, 1995 the
Expert Panel wrote: "We are confident that "high-speed" rail would produce a
very substantial diversion of travelers from air to rail transportation in the
Portland-Seattle-Vancouver corridor. (p.5)
(d) The dSEIS assumes the relative attractiveness of air service from Sea-Tac
will remain as it is today and has taken no account of the effect that a decision
not to build a 3rd runway would have on other transportation options, including
rail and the use of other airports. The fSEIS should discuss this in detail.
The fSEIS discussion should include comment on and resolve conflicts between
the data presented in the fSEIS and representations made by the Port of
Seattle to the PSRC Expert Panel regarding the Panel’s Final Decision
concerning Demand Management Issues. For example, i, the Port told the
expert panel that the Port had "identified need to have the proposed new
runway operational by soon after the year 2000." (Rebuttal of System
Management Submittals, November 6,1995, pg. 2)
The Port also verbally reassured the Panel that it would have the runway in
operation shortly after the year 2000. However, in a recent article published in
the Tacoma News Tribune (February 8,1997 "3rd Runway Unlikely to Fly Before
2005"), ," Mary Vigilante, "an FAA consultant who prepared the third runway
project's supplemental environmental impact statement" was quoted stating,
"There's not enough money to do it all at once". The fSEIS should explain in
detail the impact the anticipated minimum five (5) year in availability of a 3rd
Sea-Tac runway would have on the other alternatives, including demand
management, use of other airports, rail, & etc. The fSEIS should include a
similar analysis for a using a ten and a fifteen year delay.
Explain in the fSEIS how the introduction of the following alternatives to Sea-Tac
expansion would affect the need for a third runway:
1. Implementation of rail service on the Vancouver, BC-Seattle-Portland,
Oregon corridor.
2. Implementation of commercial air carrier service at Paine Field
3. Implementation of commercial air carrier service at other regional airports
including Bellingham International, Vancouver, BC, Portland, Oregon, Moses
Lake, Washington, Renton, WA, and other regional airports.
4. Development of Category E and F, and G traffic congestion conditions on the
major arterials serving the Puget Sound area including Interstate 5, Interstate
405, Interstate 167, Interstate 18, Interstate 520, and other major surface and
intermodal transportation routes.
(e). The fSEIS should comment on the effects which legal challenges prohibiting
Sea-Tac expansion will have upon proposed expansion of Sea-Tac airport
including the options outlined in the dSEIS . What effects will the adoption of
transportation alternatives, including alternate regional airports, rail
transportation, and other external factors have on Sea-Tac airport's traffic levels
given implementation of the Master Plan "Do-Nothing Option?
Project the effects of utilization of these alternatives on Sea-Tac air traffic
levels and associated environmental impacts through the year 2020
(f) As to the telecommunications alternative, the fSEIS should cite authorities
for its bald assertions that telecommunications are still in the Dark Ages.
Perhaps the authors of these materials have not yet heard of the Internet? A 9
per cent. reduction in air travel in & out of Sea-Tac will be much more significant
than the dSEIS material admits, when the airport begin to experience 'edge'
conditions. Provide an analysis of the savings in dollars, including annual totals,
of the 9% reduction in air travel associated with the use of new
telecommunications technologies.
6-2. Other Airports. See sec. III.1 (B).
(a) The non-appearance (in the eyes of the POS and FAA) of a 'sponsor' for a
new airport does not rule out another airport as an alternative. The assertion at
p. 3-4, Part III (B) 1. is a non sequitur. Otherwise, this whole exercise is a sham,
for the proponent of any project need simply announce that it will not sponsor
any alternative other than the preferred one, therefore there are no alternatives,
end of discussion. Cite the legal authority for the proposition stated in the cited
paragraph.
(b) Surely it is not beyond the ability of the Government of the United States of
America to encourage sponsorship of worthwhile alternatives, should they be
identified. Or, the United States can become the sponsor -- not the first time that
projects thought to be worthwhile were done under that sponsorship!
(c) In fact, as we all know, there are known sponsors for serious airports
capable of meeting the State's needs in the next century, & they should be
named in the fSEIS & their proposals treated seriously. See RCAA DEIS
Comment II-48, studiously ignored in the official responses. These sponsors
have been ignored in the past, as all know, because the proponents of the Sea-
Tac expansion (the same people who are doing this environmental review) have
the idea that the solution to future air-capacity problems has to lie in an
unsuitable location, and cannot be sought elsewhere. See following comment.
(d) The artificial limitation of the examination of alternatives to the Central
Puget Sound sub region is pretextual, a mere ploy to avoid discussing real
alternative sites. Why not frankly say that the study of alternative locations-has
to be limited for political reasons to areas controlled by the principal advocate,
the Port of Seattle, and admit that there is no interest in any solution that the
Port does not control?
(e) The remarks in paragraph 4 of the cited section are, typically, mere bald
assertions, unsupported by facts, reason, theory, or authority. The fSEIS needs
to provide at least a semblance of support, particularly in view of the facts that (i)
the dSEIS itself states that the 10-million-enplanement per annum threshold has
been passed, and (ii) operators are already moving from Sea-Tac elsewhere
(King County International Airport, Paine Field). What the dSEIS says cannot
occur is underway. Explain that. What are the future implications?
(f) We note in particular current moves by the scheduled commercial airlines
to establish air carrier service at Paine Field. (See Seattle Times Feb. 11, 1997,
p.B5) Paine Field's recently completed Part 150 Master Plan and Noise Study
Update forecasts significant levels of National and Regional air carrier service.
Forecasts for regional service with Paine Field served by regional air carriers
only, range from 81,000 to 135,000 operations per year in 2004, prior to
completion of the proposed 3rd runway. Forecasts for national service with
Paine Field served by both national and regional air carriers range from 464,000
to 776,000 annual operations in the year 2004. (See Attachment - Page B-9
from Master Plan Study) For the dSEIS to ignore the impact of diversion of Sea-
Tac's commercial passengers to Paine Field of only a fraction of the above
traffic levels constitutes an error and omission best characterized as gross
negligence. The fSEIS should assess the impacts upon Sea-Tac's projected
operations given the scenario of rapidly expanding commercial aviation growth
at Paine Field
(g) We additionally note recent regional growth in commercial operations
caused due to the addition of Vancouver, B.C.'s International Airport's 3rd
runway as well as shifts to Vancouver airport due to the recent "Open Skies"
treaty established between the United States and Canada. We also note the
growth in commercial service at Bellingham international airport. (United Airlines
"Shuttle") as well as the recent announcement that Horizon airlines is expending
$20 million dollars to expand commuter operations from Portland International
Airport in Portland, Oregon. The fSEIS should comment upon how development
at each of these airports will influence commercial aviation growth at Sea-Tac.
6-3. Demand Management. See dSEIS p. 3-5.
(a) The discussion here misrepresents the findings of the Expert Panel. The
fSEIS should not do so, but should report that the Panel found that demand
management would not work because (1) the Port refused to put demand
management into play and (2) the Panel and PSRC had no power to force the
Port to adopt demand-management measures. (Another example of exclusion
of alternatives by refusal to sponsor them.) In its Final Order on Phase II
Demand/System Management Issues issued December 8, 1995 the Expert
Panel wrote: "We nevertheless continue to have questions about the complex
and dynamic delay and capacity problems that are seen by the POS as
justifying the construction of the new runway.". The Panel noted "[t]he Panel
does not believe that it has been charged with the generalized responsibility for
determining whether there is a need to build the proposed third runway." (p.3)
(b) We question whether applicable environmental-review statutes and
regulations permit exclusion of alternatives just because there is a failure of will,
or perhaps an excess of 'won't', on the part of the sponsor and/or
environmental-reviewer. The fSEIS needs to discuss the question whether an
otherwise-viable alternative can, legally, be excluded by the whim of the
proponent of an action.
6-4. Localizer Directional Aide (LDA) Technology
(a) In its Final Order on Phase II Demand/System Management Issues issued
December 8, 1995 the Expert Panel wrote: "Improvements in Technology, including
LDA, can be expected to enhance the effective capacity of the airfield at Sea-Tac".
Provide an analysis in the fSEIS of the cost savings in landing delays to the airlines
associated with implementation of LDA technology at Sea-Tac airport as
recommended by the Expert Panel in their Final Order on Phase II Demand/System
Management Issues.
6-5. Global Positioning Satellite (GPS) Technology.
(a) In a previously submitted May 1995 report to the Committee on Transportation
and Infrastructure of the House of Representatives titled Comprehensive FAA Plan
for Global Positioning System is Needed the General Accounting Office stated that
"FAA expects that the augmented GPS will be able to support runway approaches
and landings in all weather conditions". (Report GAO/RCED-95-26, p.5, emphasis
added) This 1995 report also noted FAA's change to the year 2000 as the milestone
for the feasibility determination of GPS augmentation for supporting Category II/III
precision approaches. (p.23) Explain why the dSEIS did not consider that
implementation of GPS technology years prior to the completion date for a 3rd Sea-
Tac "bad weather" runway, which would very likely obviate the need for the runway.
(b) In a recent (December 1996) report titled Proceedings of the NASA Workshop
on Flight Deck Centered Parallel Runway Approaches in Instrument Meteorological
Conditions progress concerning utilization of derivations of GPS technology is
revealed. The report discloses that parallel approaches to runways separated closer
than the 2,500 foot discussed in the DFEIS are now being considered for use in
conjunction with this new navigational technology. (p.81) This report provides a
graphic showing parallel landing approaches under IFR meteorological conditions
are being studied with runway separations less than 2,500 feet. A United Airlines
pilot discussed investigation into utilizing the technology for conducting paired IFR
approaches to San Francisco airport's two runways which are spaced 750 feet
apart. (p.104) Sea-Tac airport’s existing runways are spaced 50 feet further apart
(800 feet) than San Francisco's. A copy of this report is attached. Explain in the
FSEIS why the dSEIS did not contemplate options including new runways more
closely separated than 2500 feet.
(c) Innovations in GPS technology have not been lost in the public media. The
enclosed article published in the June 5, 1996 edition of Aviation Week and Space
Technology reports a concept called "Traffic Conditional Approach" has been
proposed "that could permit dual IFR approach streams leading to very closely
spaced parallel runways." Explain in the fSEIS how implementation of this traffic
conditional approach technology would or would not obviate the need for a third
Sea-Tac runway.
(d) Finally, as reported in our Fall 1996 newsletter Alaska Airlines, one of Sea-Tac
airport's major carriers is now in the process of implementing GPS navigational
technology in its 737-300 fleet aircraft. (The RCAA Fall Newsletter is available on our
website. The URL is http://www.rcaanews.org/rcaa .) Explain in the fSEIS how
implementation of GPS technology would or would not obviate the need for a third
Sea-Tac runway.
(e) The fSEIS should indicate how implementation of GPS technology will affect
each of the alternatives discussed in the fSEIS, during the years 2005, 2010, 2015,
and 2020. The fSEIS should also provide a discussion of the impact of
implementation of GPS technology allowing "poor weather" IFR approaches at Sea-
Tac upon the stated "purpose and need" for the 3rd Sea-Tac runway, the need for a
"bad-weather" runway.
6-6. Blended Alternative. See discussion at dSEIS p. 3-6.
(a) The discussion here is fatally flawed by the mistaken notion that each
alternative standing alone must be able to satisfy the need for the proposed
project. The discussion should address the combination of non-project
alternatives, including those referred to in earlier comments -- rail, medium-
speed rail, use of other nearby airports, teleconferencing & related technologies,
LDA, GPS, increased efficiencies (especially with regard to the below-60-seat
airlines, consuming 38 to 40 percent. of the operations capacity). Provide a
matrix which describes the estimated effect on future Sea-Tac air traffic
operations by year, through the year 2020, in five year increments. Analyze the
effects on Sea-Tac traffic and delay costs assuming the following factors:
1. Assume medium and high-speed rail diverts existing Sea-Tac traffic
levels in the following ranges: 5-10%, 10-15%, 15-20%, 20-25%.
2. Assume implementation of LDA technology which obviates the need for
IFR approaches at Sea-Tac in the following ranges: 90-100%, 80-90%, 70-
80%, 60-70%
3. Assume FAA issues feasibility determination for implementation of GPS
technology which obviates the need for all IFR approaches at Sea-Tac in
the year 2000.
4. Assume new innovations in telecommunications technologies divert
existing Sea-Tac traffic levels in the following ranges: 5-10%, 10-15%, 15-
20%, 20-25%.
5. Assume utilization of alternate regional commercial airports divert
existing Sea-Tac traffic levels in the following ranges: 20-30%, 30-40%, 40-
50%, 50-60%, 60-70%
(b) The delay discussion on p. 3-7 needs detailed cross-references to
wherever it is in the FEIS that delay matters were discussed in depth (including
comments and responses thereto).
PART 7: OTHER COMMENTS
The comments in this Part are organized as follows:
A. Planning Horizon
B. Surface Traffic
C. Cost
D. Methodological Concerns
PART 7(A) -- Planning Horizon Issues
7(A)-l. Planning Horizon Should Be At Least Year 2020.
(a) The planning horizon for environmental impacts should extend at least
to the prior planning horizon originally established in the Master Plan Update for this
entire exercise, the year 2020. See dSEIS p. 5-1. It seems absurd to plan to put a
facility in operation in the year 2005 or 2006 and then refuse to look at impacts
taking place beyond the year 2010. It defies human understanding to suppose that
there would be no impacts five or six years after the third runway's expected coming
into use.
(b) Do the SEIS preparers assert that there will be no adverse impacts
from the proposed actions after the year 2010?
(c) Is it not the fact that the post-2010 years are ignored because
preliminary studies show that the impacts will be progressively more severe, and the
proponents of the project do not wish the public to know about those impacts? If not,
give a valid explanation consistent with prior use of 2020 as the planning horizon in
this environmental-review process.
(d) State the planning horizons used in PSRC transportation planning
processes, including aviation planning. If there are differences between the PSRC
planning horizons (i.e. PSRC's Vision 2020) and those used by the SEIS preparers,
explain them & provide justifications for deviating from the PSRC methods and time
table.
7(A)-2. If Planning Cannot Be Done More Than 14 Years in the Future, Can Any
Rational Planning Be Done in This Exercise? The putative reason for not doing the
work beyond year 2010 --high volatility of travel demand -- is an excellent reason for
not engaging in air-traffic forecasting as well, and therefore for not doing this project.
(a) Can rational planning be done in light of the constraints suggested by
the dSEIS (p. 5-1)?
(b) Is the economy to be burdened with a 2 or 3 billion dollar project with
over 4 billion dollars of adverse impacts on the basis of projections that do not
include consideration of future events that are reasonably foreseeable, although
perhaps not in exact arithmetical terms? Or does reasonable foreseability only apply
to measuring the harm done by the project, not the alleged benefits?
PART 7 (B) -- Surface Transportation Issues
7(B)-l. Map Problems.
(a) Ex. 5-1-1 (simplified local highway map) should indicate whether it is
current or includes proposed but as-yet-unbuilt roadways. Perhaps both are
needed.
(b) The hexagons with numbers, described as percent distribution of
airport traffic, do not convey much meaning, and need at least a text explanation
and a suitable cross-reference thereto in the table itself.
7(B)-2. Mitigation Issues.
(a) Construction. (This matter relates to Part I of these Comments,
Construction Impacts.) The HOK study, referred to in earlier comments, indicates
that extraordinary wear and tear will occur to local roadways as the result of the
colossal number of fill hauling trips. No mitigation is proposed in the dSEIS to the
State, County, or affected cities for an exercise that apparently will be destructive.
The fSEIS should examine the roadway mitigation problem & other mitigation
issues and make realistic proposals.
(b) Long Term. Who is to bear the cost of fixing traffic messes that will
occur long-term as the result of Sea-Tac expansion? Is this another burden to be
thrown off on the local people and their local governments, all for the benefit of
Airport users who pay little to no taxes to the local governments, and who mostly
reside elsewhere?
(c) The long-term mitigation problem is particularly poignant in the case of
air cargo. The Port of Seattle operates at a yearly loss of over $35 million, which is
made good by real-property taxes. While it is claimed that none of this loss comes
from aviation activities, we have seen nothing to rebut the contention that this is at
best a mere accounting convention. Air cargo, like marine cargo, passes through
here on its way to & from remote destinations. Operating losses and unmitigated
adverse impacts amount to subsidies given by the taxpayers and local residents to
business activities in other States and in foreign countries, given as the dSEIS
suggests (The FAA being co-author of the dSEIS) by our tax-exempt Port district. If
this is being done at federal initiative, the federal government should pick up its fair
share of the mitigation bill (in the billions, over-all); if this is only done for the
convenience of the Port and its customers, then the Port should be the vehicle for
redress of adverse impacts. The fSEIS needs to sort this all out, for surface traffic
impacts, for all other impacts as well.
PART 7(C) -- Cost
7(C)-l. Are the Cost Estimates Reliable? Meaningful? It is conceded at p. 5-
4-1, referring especially to third-runway work, that detailed design & construction
plans have not been prepared.
(a) How reliable are the construction time lines suggested in either the
FEIS or the dSEIS?
(b) How reliable are the cost estimates suggested in either the FEIS or the
dSEIS? We note that only several weeks ago the Port announced the estimated
cost of just the 3rd runway alone jumped by $132 million dollars.
(c) It appears that no engineers have been involved in this work (none are
identified in the list of preparers of the dSEIS), and neither the FEIS nor the dSEIS
examines the work that will need to be done to construct the third runway. (i) Is this
huge earth-fill work practical? We are aware that the 1994 EIS for improvements at
the Albuquerque Municipal Airport concluded that an runway extension with up to
150 vertical feet of fill required -- closely comparable to the Preferred Alternative for
Sea-Tac -- was impractical. (ii) Will the fill sustain the stresses to be placed on it by
the aircraft that are expected to use it? Provide a copy of the geo-technical report
prepared by a registered professional engineer which substantiates this.
(d) Cite the relevant studies that support your response to this comment,
and quote relevant portions that indicate that this work can be done. Identify the
individual engineers and engineering firms who have done the work on the third
runway to date.
7(C)-2. Cost-Benefit Ratio. Where are the cost-benefit studies required for this
dSEIS? If they exist, including them with the fSEIS. Alternatively, indicate locations
where they may be obtained or perused.
7(C)-3. Cost-Benefit Ratio. Perhaps the reason why it has been decided to
shorten the planning horizon to the year 2010 is to avoid the problem discussed in
this comment: the third runway will outlive its utility in a very few short years after it
opens for business, and the number of those years shrinks as the new traffic
forecasts are made. What sense does it make to spend all these billions of dollars
for this short-term fix, when the forecasts indicate that the need for an alternative
REGIONAL (not Seattle-Tacoma local) solution will be upon not more than six years
after and more likely before the opening date for the proposed 3rd runway? The
fSEIS should discuss this problem in fullest detail.
7(C)-4. What Will Happen When Capacity Limits Are Reached? Given the
onrush of traffic and the likelihood that even if the third runway is built Sea-Tac will
be far beyond capacity in a few years, what is proposed for the next action to
alleviate the capacity crunch? Is the fourth runway now a 'gleam in anyones eye'? Or
is it expected that technological improvements will permit another capacity increase
at Sea-Tac?
7(C)-5. Future Aircraft. What actions are being considered to cope with the
advanced aircraft of the future now under study, such as the so-called 'China
Clipper', super-jumbo subsonic jets, and others?
7(C)-6. Rationale for Scheduling-Change. Why do Port staff now recommend
that the third runway be operational by 2005 instead of the original target date of
2000. See dSEIS, p. 2-21. What was reexamined, to what effect, and where are the
results of the reexamination published?
7(C)-7. Financing Concerns. Careful reading and re-reading of Part 3 A,
second unnumbered paragraph of first bullet point, p. 2-21, together with the first
sentence on p. 2-24, leads us to conclude that the operative reason for the staff
suggestion in this dSEIS to reverse the order of construction of the third runway and
associated groundside projects --non-runway projects first -- is the unavailability of
financing for the third runway during the time frame posited by the Master Plan
Update and its FEIS. Is this a correct reading? If not, what is the correct reading, &
why is the order of construction of the two major components proposed to be
changed?
7(C)-8. Contingency Planning. There should be discussion in the fSEIS of
contingencies that may arise from further delay in various phases of the over-all
expansion project. In particular, the fSEIS should look carefully at the contingency
that funding for the third runway will still not be available at the now-planned start
date. Would it be rational to construct the landside facilities if third runway financing
will not be available (whether at the time hoped for, or at all)?
PART 7(D) - Methodological Concerns
7(D)-l. Incorporation of Applications by Reference.
(a) It is inappropriate to incorporate documents by reference (p. 5-5-2) without
providing them for review.
(b) Do the preparers of this SEIS expect that the Port Commissioners will
troop down from Seattle to the Port's Engineering Office at the Airport, or the
FAA's shop in Renton, to read these documents
(c) Do the preparers think that it is practical for all the interested agencies,
cities, special districts, community groups, individual citizens, and so on to
review documents only available in the FAA's or Port's offices, with only one
copy per office available for review?
7(D)-2. Incorporation of FEIS Appendix R by Reference. In the Air Quality
section of the dSEIS, there is a general reference to air quality information
appearing in Appendix R, the appendix to the FEIS setting out the official
responses to comments on the DEIS. The dSEIS text then says that Appendix R is
incorporated by reference.
(a) The Appendix should not be included by a general reference. Rather,
reference should be made to particular responses that deal with the particular
issue under discussion in the dSEIS or fSEIS. The air-quality section of the
dSEIS should be revised accordingly in the fSEIS.
(b) This is a particularly aggravating practice in the instance of Appendix R for
two reasons: (i) the rather scattered nature of the information in the Appendix;
(ii) the Appendix was, unaccountably, not furnished to numerous commenters.
7(D)-3. Incorporation by Reference -- Another Instance. Exactly what parts of
the FEIS are 'incorporated by reference' in the second full paragraph on p. 5-1?
Give page numbers. Better yet, set out the material.
7(D)-4. Cumulative Impacts. See sec. 5-3 5 "Cumulative Impacts", p. 5-3-7.
(a) The projects or developments referred to here should be specifically
identified, one by one, and the present state of planning of each should be set
forth.
(b) Is it not true that ranges of possible impacts from these various projects
can be forecast and considered?
7(D)-5. Cumulative Impacts. Subsection 5-6 1 (D) p. 5-6-5, suffers from the
same defects as other discussions of cumulative impacts in the dSEIS.
(a) Surely the other pending projects in the Airport area are well known to the
preparers. Is this not so?
(b) Surely the statutes and regulations require the preparers at least to make a
colorable effort to gauge the impacts of other known projects. Is this not so?
(c) The fSEIS should touch on known pending projects and at least give
reasonable ranges of potential, cumulative impacts.
7(D)-6. Still No Index. Where is the index? Why do the Port and FAA refuse to
provide indices to these environmental documents? Alphabetizing the table of
contents (as was done for the FEIS) is not an index, for such a construct does not
tell the reader where discussion of various topics can be found --the very purpose of
an index. This is particularly disabling when trying to find discussion of such
important matters as noise impacts, air quality, & water quality, where much
important discussion occurs in the form of comments and responses, for which
there is no index or other guide provided. We asked for an index in our scoping
comments, we asked for an index in our DEIS comments, we ask again. By the
way, there are perfectly adequate computer word-processing programs that will
construct a fair-to-good first draft index at, so to speak, the push of a button. The
results of that would be a lot better than the nothing that has been provided to date.
PART 8: Request for Extension of Time to Provide Additional Comments
8(A) Late Arrival of dSEIS Documents in Local Libraries - The dSEIS is
almost 1,000 pages long, It is technically difficult and time consuming for the public
to read and understand. Copies of the document have not been available to
members of the public most affected by the proposed action. Most local libraries did
not receive copies until the last week of February. The copy of the dSEIS at the
Burien library is date stamped "Received Feb 25, 1997", one week prior to the
public hearing.
The Des Moines library whose patrons include residents of one of the areas
which would be most impacted by the project did not have a copy of the dSEIS
available to the public as of noon on March 4, the day of the public hearing. Only 16
copies of the dSEIS have been provided at public libraries, one per library. The
dSEIS at each library is available for reference only. The FAA/Port presumes 16
copies of the document are sufficient to notify over 200,000 citizens of the proposed
action's environmental impacts.
8(B) Cost of dSEIS Documents Copies of the dSEIS cost $60 dollars each,
exorbitantly priced for even citizens of moderate means, not to mention low income
residents who would be most impacted by the proposed action.
8(C) Lack of Availability of dSEIS Documents It took the Port and the FAA
a year to write the draft supplemental EIS. The public should have many more
copies available at reasonable cost, at least 90 days for review and comment, and
at least two more local public meetings to review the proposal in order to provide
meaningful public comment concerning the impacts on our communities.
8(D) Unavailability of Documents Referenced in dSEIS Documents which
concern elements of the proposed action which have the most significant impacts to
the area were not even included in the SEIS. For example; the Wetlands Mitigation
Plan and Miller Creek Relocation Plan. A check with the reference librarian at the
Burien Library on March 5 determined neither of these documents have been logged
into King County's Library Catalog System and also that neither document is
available at the Burien Library for public review and comment. A check with the Des
Moines library on March 6 similarly determined that neither the Port's Wetland
Relocation Plan or the Miller Creek Relocation Plan documents were available for
public review at the Des Moines library.
8(E) Problems with March 4 Public Hearing A public hearing at SEA-TAC
airport on a weekday (March 4) during rush hour was the worst possible
location/time/etc. to solicit meaningful public comment for this SEIS. Many citizens
were deterred by Sea-Tac airport's exorbitant parking fees. The public notice of the
hearing did not indicate whether free parking would be provided for low income
residents who wished to testify at the public hearing.
8(F) Request for Additional Public Hearings and Extension of Public
Comment Period To remedy the improper conduct of this SEIS public comment
process we strongly recommend at least two evening meetings in the local cities of
Burien, Des Moines, Tukwila, Sea-Tac, Federal Way, Normandy Park, as well as
communities in the Rainier Valley, Columbia City, Beacon Hill, Mercer Island,
Magnolia, Capitol Hill and other affected areas, etc. should be scheduled and held to
study the dSEIS. The present public comment period should be extended. After the
public meetings are held a minimum 90 day public comment period should be
allowed to permit members of the public to review the proposed action and make
informed comments upon the proposal.
Comments of the Regional Commission on Airport Affairs
(RCAA) on the Draft Supplemental EIS (dSEIS) to the
Seattle-Tacoma International Airport Master Plan Update
http://www.rcaanews.org/rcaaseis.htm
[Back to Welcome][Back to Library Catalog]