Back to page 1
striped bar
October 31, 2003
 

Supreme Court To Hear Appeal of State
Wetlands Certificate on 18 November

Attorneys for the Airport Communities Coalition, Citizens Against Sea-Tac Expansion, Port of Seattle, & Department of Ecology will appear before the nine Justices of the Washington State Supreme Court on Tuesday, November 18 for oral argument on the State’s water-quality certificate for third-runway work. An hour has been set aside for argument, probably starting between 9.45 and 10 a.m. in the Temple of Justice, Olympia.

No new evidence, witnesses, or public comments will be heard, only legal arguments. So there are no plans for a chartered bus trip to Olympia. However, the arguments will probably be presented ‘live’ through the Internet, www.tvw.org. If not webcast live, a voice record of the proceedings will almost certainly be posted in tvw’s archives of Supreme Court proceedings at a later date.

Immediate decision not expected

An immediate decision is not expected. The usual practice is for the Court to issue a written decision several weeks after oral argument, after consideration of the argument, and, in this case, the nine separate written legal memoranda (briefs) on file.

Under sec. 401 of the federal Clean Water Act, before the Port of Seattle could obtain permission from the U.S. Army Corps of Engineers to destroy wetlands with third-runway fill, the Port had to obtain a certificate from the State to the effect that the work would likely not violate State water-quality standards.

The Port’s first application for this certificate, filed in December 1996, failed. The second (revised) application was filed in September 1999. It too was inadequate, & the Port withdrew it rather than have Ecology deny it. On a third try, the certificate, with conditions, was issued by the Department of Ecology in August 2001. Airport Communities Coalition (ACC) experts advised that the conditions were not adequate to protect water quality, & so an appeal was taken to the state Pollution Control Hearings Board by ACC, joined by C.A.S.E.

Court will review rulings of state
Pollution Control Hearings Board

After a two-week trial, that Board ruled in August 2002 that the conditions were inadequate, & imposed 16 additional requirements, designed to give assurance that the runway work would actually be in compliance with State standards. It is that ruling which is under challenge now in the Supreme Court.

The Port of Seattle & the Department of Ecology will argue that the certificate was fine as it was, before the Board acted, & that the Board exceeded its legal authority, & went beyond scientifically defensible requirements. In particular, the Port & Ecology claim that the Board went too far in relying on its own expertise, & the testimony & other evidence from the two-week trial. The Board should have relied on Ecology's expertise, not its own, they say.

The Board itself, very unusually, has filed a brief (written argument) with the Court, explaining the legal authority for its methods of making decisions. However, the Board will not be represented at the oral argument.

ACC & C.A.S.E. support the 16 conditions added by the Board, but they will tell the Court that Board should have imposed even more stringent conditions on the project.

The appeals focus on two central, but highly technical, disputes: how much pollution to allow in fill materials for the runway, & how to deal with the immediate impact of the project on local streams.

How much pollution in the runway fill?

The runway embankment eventually will require 19.84 million cubic yards of fill. About one-fourth of this amount has been brought in, leaving about 15 million yards to go. The Port, with Ecology's concurrence, wants to be able to use material contaminated with arsenic, lead, petroleum by-products, & other pollutants. The community groups want clean fill, not materials already contaminated elsewhere. From the Port's point of view, it is ultimately all about money. It is cheaper to accept dirty fill from clean-up sites (as has already happened in this project). It is cheaper to buy fill that has been dusted with arsenic & lead fall-out from the old smelters at Ruston & Everett than clean materials from farther away. It is cheaper to do fewer tests, & to use less-rigorous tests.

The Pollution Control Hearings Board ruled that contamination in the fill should not exceed natural background levels. Among other things, that eliminates fill contaminated by petroleum by-products, leading the Port to claim that gasoline is a naturally-occurring substance in the Central Puget Sound! The Board did not agree. The Port argues that this "natural background" standard is not required to prevent degradation of water quality, & that the law does not allow the Board to impose such a rule. The community groups, of course, argue just the opposite.

The "poster child" in this dispute is arsenic. Arsenic is a cumulative & deadly poison. Even at low exposure, it builds up in the human body, until it reaches toxic levels - often only noticeable after decades. There are no easy treatments for arsenic poisoning. The substance occurs naturally in many parts of the world, including Western Washington, though at very low, non-hazardous concentrations. Much more arsenic also occurs throughout the coastal part of the Central Puget Sound region, as a by-product of many years of unregulated smelter operations at Ruston (Tacoma) and at Everett. This means that most near-by gravel pits are likely to have arsenic levels above background. The concern is that concentrating a lot of arsenic-contaminated material in the runway embankment would create a health hazard, as the arsenic is gradually carried downward into the local streams & even the Highline aquifer, at levels well above background.

Before the present case began, the Port in at least four instances accepted fill that was contaminated with arsenic to unacceptable levels. When such levels were detected in initial screening, the Port simply switched to another test (the "SPLP test") that does not detect arsenic at low, but still hazardous, concentration. In this way, they "passed" otherwise unacceptable fill. An ACC lawyer exposed this practice during cross-examination of a Port expert witness during the PCHB hearing. The Board ruled that this practice had to stop.

Earlier this year, the Port persuaded the Legislature to pass a highly-controversial special statute to allow this practice to continue. ACC, C.A.S.E., and a coalition of local environmental groups from around the State are challenging that statute as unconstitutional.

If the Port would simply insist that its suppliers provide clean fill, half the issues in this appeal would disappear.

Wetlands, stream flow, water rights

In general, the Board decided that the Port's plans were not adequate to protect wetlands and local streams.

Wetlands will be destroyed, with long-term environmental damage, if the runway project goes forward, & so they must be replaced. Experts disagree as to just what should be done, but the Board ruled that the Port needed to do more, at higher cost. Streams are healthiest if they have neither too little nor too much water. If the wetlands are not fully replaced, there will be too much water in local streams in wet weather. Too much leads to flooding. Some flooding is natural, even desirable. But severe flooding sweeps away the soil on which stream vegetation depends, destroys the gravel beds where salmon spawn. Repeated severe flooding kills a stream. Wetlands help prevent this.

Wetlands also release water during the Summer dry spell, preventing streams from running dry. Much of the rain that would fall on the new runway, taxiway, &c., would be diverted into the Airport's industrial wastewater system for treatment & for discharge out of the area, just as now happens to rainfall on the existing runways. In the dry season, this robs Des Moines, Walker, and Miller Creeks of vital water. With a third runway, the impacts of this diversion would be unacceptable. The Port's answer to this difficult problem is a plan to build huge underground vaults, in which wet-weather rainfall would be stored, for bit-by-bit release, as needed, in the dry period. Not only is this hugely expensive but also it raises the question of whether the Port has the legal right to latch onto water that belongs to all of us. The Board ruled that the Port would need a legal water right to make such a diversion. The Port does not own such a water right, has not applied for one, & has little chance of obtaining it.

 


©RCAA 2003
Regional Commission on Airport Affairs is a
nonprofit, nonpartisan citizens' organization
19900 4th Ave S.
Normandy Park, WA 98166-4043
(206)824-3120
E-mail us

 
Back to Front Page

  • Opening and response briefs of all parties are posted in the RCAA library. Click here to go to that section.
  • PCHB Ruling
 

www.tvw.org will either carry the arguments live or post them on their website.

TIA July 2003, Environmental Groups Join Lawsuit Over Dirty Fill Bill