August 12, 2002

No Green Light for Third Runway:
State Appeals Board Says Port Must
Do More To Protect Environment

A state appeals board ruled today (12 August 2002) that the Port of Seattle, operator of Sea-Tac Airport must meet new environmental conditions if it plans to go forward with its proposed third runway at the Airport. Previous conditions laid down by the Department of Ecology in a certificate issued under provisions of the federal Clean Water Act are supplemented by heavy new requirements.

In a case brought by two groups opposing the runway project, the Pollution Controls Hearing Board (PCHB) ruled that several new conditions had to be added to existing environmental plans of the Airport in order to provide "reasonable assurance" that State water-quality standards will not be violated, if the project were built as planned.

At an earlier stage, the PCHB had granted a stay of the effectiveness of the certificate, on the ground that runway opponents had shown a "likelihood of success" on the merits of the appeal in several issues. In its final ruling today, the Board ruled in favor of the opponents on most of those issues. Here are highlights:

A steady and certain supply of supplemental water to overcome low streamflow in near-by creeks.

The Board said that the Airport is not legally allowed to impound rainfall for this purpose without a valid water right (which it does not have and probably cannot get). This was a key issue raised by runway opponents, upheld by the Board—the Port must now obtain valid State water rights to guarantee that it will have an adequate supply of supplemental water to add to near-by streams in Summer dry periods to keep them healthy, as required by state water-quality rules.

New and improved plans to deal with the persistent contamination of run-off from the Airport, which impacts local salmon-bearing streams.

The Board specifically held that the testing methods preferred by the Airport were not satisfactory to provide accurate data on the nature and extent of stream pollution. The Board totally rejected claims by the Department of Ecology and the Port that there no demonstrated violations of water quality in streams coming down from the Airport. The Airport's own testimony proved just the reverse. The Airport will now be required to find ways to intercept contamination by various metals, a problem shrugged off by the Department of Ecology in granting approval to the project.

A better way of preventing contaminated fill from being brought in, and tighter rules about what is acceptable

The Board agreed with runway opponents that Ecology was allowing too much contamination in fill material for the runway embankment; this contamination can seep into local streams and groundwater. Better testing methods for imported fill are now required, and the limits for acceptable contamination are sharply reduced. While the Port and Ecology were content with fill contaminated by gasoline and other petroleum products, the PCHB set a new limit of zero for such materials. Limits for mercury, cadmium, lead, selenium, nickel, and chromium were drastically cut by the Board. One small comfort for Airport management: the Board did not require that they find and remove contaminated materials previously delivered.

A better plan for replacing 22 acres of wetlands

More than 22 acres of wetlands will filled or irreparably damaged if construction proceeds. The Board agreed with critics that the plans for mitigation did not restore important wetland functions that would be lost forever. This was a point discussed at length in the PCHB stay order as being an issue on which critics would likely prevail—and the final order confirms this initial ruling. The Airport must now create new wetlands, or restore more old wetland acreage, in the vicinity of the runway project. In an initial reading of the opinion, it is not clear just how much more acreage will be required, but it is significant. However, the Board disagreed with the contention of many critics that the supplemental wetlands replacement project in Auburn was improper.

Larry Corvari, President of the citizens' group Regional Commission on Airport Affairs, said "This is a helpful ruling. It puts some teeth back into our environmental laws. The Department of Ecology caved in, but the Board did not. On key points—water rights, stream contamination, and fill contamination, the Board has come down on the side of those who saw environmental disasters looming."

Mr. Corvari continued, "The Airport persuaded Ecology to approve the project first, and let the Airport fill in the details later on. The way I understand the ruling, the Hearings Board is requiring a lot more of the details to be spelled out. And it's very significant that the Board repeatedly mentioned that all the conditions should be enforced as part of the Airport's new pollution permit. Here's the missing enforcement mechanism, at long last."

Asked whether the runway project can go forward after this unfavorable ruling, Mr. Corvari said "Of course, that's up to the Commissioners of the Port of Seattle. They can try, if they wish, to meet these conditions. But they've spent $342 million at least so far, and they have no cost estimates in hand for the conditions imposed by Ecology, or for these new requirements from the Board. This begins to look like a project that will devour all the Port's money for a decade to come. This would be a good time to mothball the runway and look for a Plan B. Fortunately, there is such a plan - pick the best site for a second regional airport - someplace where the environmental problems are easy, not impossible, someplace that isn't in the middle of a major metropolis, someplace where the runway won't be knocked out in the next earthquake. There are whole counties crying out for new business, who would love to be considered for a big airport project—counties with plenty of flat, dry land to spare."

On one issue of great concern to many, the Board accepted the Airport's reassurances that the massive runway embankment was highly unlikely to fail in a foreseeable earthquake. The Board also chose not to use the highest standard for seismic safety on the ground that the third runway would not be "lifeline" [truly vital] facility. Therefore, a less-onerous standard of frequency may be used. The Board may have erred on this point, because their rationale is that there are other near-by airports to take the slack in case of earthquake damage to the third runway. But the Nisqually Earthquake of 2001 should have taught us that an earthquake that can do damage at Sea-Tac will do even more damage to Boeing Field - the only airport near-by that is in any way set up to take over major air-carrier functions if Sea-Tac is crippled.

The appeal was brought by a coalition of local governments, the Airport Communities Coalition (ACC). This group consists of the cities of Burien, Des Moines, Federal Way, Normandy Park, and Tukwila, and Highline School District No. 401. Part-way through the pre-trial proceedings, a citizens' group, Citizens Against Sea-Tac Expansion (CASE) joined the appeal.

The Airport Communities Coalition was represented at the hearing by Peter J. Eglick and Michael P. Witek, of the Hellsell Fetterman firm, and by Rachel Paschal Osborn. The intervenor, Citizens Against Sea-Tac Expansion, was represented by Richard A. Poulin, who is associated with the Smith & Lowney firm.

The Department of Ecology was represented by Joan M. Marchioro, Thomas J. Young, and Jeff B. Kray, all from the Attorney General's office. The Port of Seattle was represented by house counsel—Linda J. Strout, General Counsel for the Port, and Traci M. Goodwin, Senior Counsel - and also by two law firms; Roger A. Pearce and Steven G. Jones, from Foster Pepper & Shefelman, and Jay J. Manning, Tanya Barnett, Gillis E. Reavis, from Brown Reavis & Manning.

The RCAA library contains a full record of the hearing on videocassettes, with an index to the proceedings, which may be checked out for use at home.


©RCAA 2002
Regional Commission on Airport Affairs

is a nonprofit citizens' organization
19900 4th Ave S.
Normandy Park, WA 98166
(206)824-3120

E-mail us


Seattle Times

Seattle PI

Large version of map
Adobe Acrobat (.pdf) version of map

Links:
Washington State Pollution Control Hearings Board

Department of Ecology


Port of Seattle--News Releases

Miller Creek, A Place of History Peace, and Change